Ohio Valley Environmental Coalition v. Aracoma Coal Co.
AI Case Brief
Generate an AI-powered case brief with:
Estimated cost: $0.001 - $0.003 per brief
Full Opinion
Reversed, vacated and remanded by published opinion. Judge GREGORY wrote the opinion, in which Judge SHEDD joined. Judge MICHAEL wrote a separate opinion dissenting in part and concurring in part.
OPINION
This appeal concerns a challenge by Plaintiffs-Appellees Ohio Valley Environmental Coalition, the Coal River Mountain Watch, and the West Virginia Highlands Conservancy (hereinafter referred to collectively as âOVECâ) to the U.S. Army Corps of Engineers (âCorpsâ) issuance of
Separately, in an order dated June 13, 2007, the district court provided declaratory relief to OVEC, holding that the stream segments linking the permitted fills to downstream sediment treatment ponds were âwaters of the United Statesâ and that the Corps lacked authority under the CWA to permit discharge from the fills into the stream segments.
The Corps now appeals these two orders. For the reasons set forth below, we reverse and vacate the district courtâs opinion and order of March 23, 2007, and vacate the district courtâs injunction. We also reverse the district courtâs June 13, 2007, grant of declaratory relief and we remand for further proceedings consistent with this opinion.
I.
The mountaintop removal method of surface coal mining, pioneered in West Virginia, involves the blasting of the soil and rock atop a mountain to expose coal deposits below. While mining operations are ongoing, the overburden is hauled or pushed into adjacent valleys. This excavated overburden is known as âspoil.â Once the coal has been extracted, efforts are made to re-contour the mountaintop by replacing the removed overburden, but stability concerns limit the amount of spoil that can be returned to the area. In its natural state, the spoil material is heavily compacted; once excavated, however, the loosening of the rock and soil and incorporation of air causes significant swelling. As a result, large quantities of the blasted material cannot be replaced, and this excess spoil (âoverburdenâ) remains in the valley, creating a âvalley fillâ that buries intermittent and perennial streams in the process.
Water that collects in the fill must be moved out to ensure the fillâs continued stability. Thus, an underdrain system is constructed by placing large boulders up to and above the ordinary high-water mark of the stream. The collected water is then channeled into a treatment pond, where sediment from the runoff is allowed to settle. Sediment ponds usually are constructed in existing streambeds, using earth and rock to create an embankment. After sediments have settled out of the fill runoff, the treated water is discharged from the sediment pond back into existing streams. When practicable, a sediment pond will be constructed in the streambed immediately adjacent to the end (or âtoeâ) of the fill. But, because West Virginiaâs steep, mountainous topography often prevents this kind of positioning, a short stream segment is frequently used to move runoff from the fill downstream to the sediment pond. Once a valley fill is stabilized, the embankments of the sediment pond are removed, and the ponds and the stream segments are restored to their pre-project condition.
Much of the impact of a valley fill project is felt by headwater streams. Head-water streams are small streams that form the origin of larger streams or rivers, and may be intermittent or ephemeral. Intermittent streams receive their flow from both surface runoff and groundwater discharge, while ephemeral streams rely on
OVEC initiated this challenge in September 2005 in the United States District Court for the Southern District of West Virginia, shortly after the Corps issued an individual valley fill permit and accompanying Combined Decision Document (âCDDâ) to the Araeoma Coal Company for the Camp Branch Surface Mine project (âCamp Branchâ) under its CWA § 404 authority.
In addition to the Camp Branch permit, OVECâs Third Supplemental Complaint raised challenges to the individual § 404 permits issued to the Elk Run Coal Company for the Black Castle Mine (âBlack Castleâ), and to Alex Energy, Inc., for the Republic No. 1 and Republic No. 2 Surface Mines (âRepublic No. 1â and âRepublic No. 2â). The Republic No. 1 challenge was ultimately dismissed on ripeness grounds, but a challenge raised in a separate complaint to the individual permit issued to Independence Coal Company for the Laxare East Surface Mine (âLaxare Eastâ) was consolidated with this proceeding. Each of the affected companies intervened as defendants in the action, as did the West Virginia Coal Association.
All together, the four challenged permits authorize the creation of 23 valley fills and 23 sediment ponds, and they impact 68,841 linear feet of intermittent and ephemeral streams, or just over 13 miles.
OVECâs Third Supplemental Complaint charged that the Corpsâ issuance of the § 404 fill permits for these mining projects violated both substantive and procedural provisions of the CWA and NEPA, and were âarbitrary, capricious, and an abuse of discretionâ under the APA. According to OVEC, the Corps was required under
Trial in the case was originally scheduled for June 20, 2006, but on June 16, on the Corpsâ motion, the district court remanded the permits to the Corps and stayed the proceedings. Almost a month later, the Corps reissued the permits, but this time with a supplemented administrative record that incorporated new comments from the public and the parties, including the reports prepared by OVECâs proposed expert witnesses. The district court lifted its stay on July 26, and a six-day bench trial was held in October 2006.
The district court granted judgment in favor of the plaintiffs on March 23, 2007, rescinding the permits, enjoining the Corps and Intervenors from taking any action under those permits, and remanding the permits to the Corps for further proceedings consistent with the courtâs order.
The district court found, inter alia, that the probable impacts of the valley fills would be significant and adverse under both the CWA and NEPA; that the mitigation plans for each permit were not sufficient to compensate for those adverse impacts; that, in each permit, the Corps improperly limited its scope of review under NEPA to look only at the impact on jurisdictional waters rather than the broader impact of the entire valley fill project; and, finally, that the Corps inadequately evaluated the cumulative impacts of the projects.
On June 13, 2007, the district court granted summary judgment to OVEC on a separate claim under which the plaintiffs sought a declaratory judgment that the stream segments running from the valley fill toes to the sediment pond embankments are âwaters of the United States,â and that the Corps thus did not have authority to permit the discharge of pollutants into these segments with a CWA § 404 permit. According to the district court, mining operators who wished to discharge runoff from the fill into a stream segment needed to obtain a CWA § 402 permit from the EPA or proper state authority. On September 13, 2007, the district court granted, pursuant to Federal Rule of Civil Procedure 54(b), the Interve-norsâ motion for entry of final judgment on the June 13 order.
On appeal, the Corps contends that it is entitled to deference on its determination about the scope of its NEPA analysis and that its findings on individual and cumulative impacts and mitigation were not arbitrary or capricious. The agency further argues that its interpretation of its CWA regulations â treating stream segments and sediment ponds as part of a unitary waste treatment system and thus excepting them from separate CWA § 402 per
II.
We review de novo a district courtâs findings on an administrative record. See Crutchfield v. County of Hanover, 325 F.3d 211, 217 (4th Cir.2003). This de novo standard applies to questions of both law and fact. See id.
Both NEPA and CWA claims are subject to judicial review under the APA, 5 U.S.C. § 706 (2006). For all agency actions, a reviewing court must set aside the action if it is found to be âarbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.â 5 U.S.C. § 706(2)(A) (2006); Citizens To Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 413-14, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971).
III.
A complex statutory framework under-girds the regulation of valley fills and associated sediment ponds, and it is this framework that provides the foundation for our opinion. Thus, we begin with a brief overview of the relationship of the four statutes that affect the scope of the Corpsâ authority to issue fill permits in connection with mountaintop coal mining operations: the Surface Mining Control and Reclamation Act of 1977 (âSMCRAâ), 30 U.S.C. § 1201 et seq. (2000), the CWA, NEPA, and the APA.
A.
Congress passed SMCRA in 1977 to âestablish a nationwide program to protect society and the environment from the adverse effects of surface coal mining operations.â 30 U.S.C. § 1202(a) (2000). Congress also recognized a need, however, to âstrike a balance between protection of the environment and agricultural productivity and the Nationâs need for coal as an essential source of energy.â 30 U.S.C. § 1202(f) (2000). In striking this balance, SMCRA utilizes a âcooperative federalismâ approach, allocating responsibility for the regulation of surface coal mining among both state and federal agencies. Bragg v. W. Va. Coal Assân, 248 F.3d 275, 288 (4th Cir.2001).
Under SMCRA, states have âexclusive jurisdiction over the regulation of surface coal mining and reclamation operationsâ on non-Federal lands, so long as their regulatory program has been approved by the Secretary of the Interior as satisfying the Actâs minimum requirements.
Regulation of the disposal of excess spoil material from surface coal mining opera
B.
An SMCRA permit by itself, however, does not suffice to allow a mine operator to construct a valley fill in conjunction with its mountaintop removal activities. Mining companies must also obtain permits certifying their projectâs compliance with the CWA. The CWA aims to ârestore and maintain the chemical, physical, and biological integrity of the Nationâs watersâ by eliminating âthe discharge of pollutants into the navigable waters.â 33 U.S.C. § 1251(a)(2000). In the surface mining context, three sections of the CWA are relevant to the permitting process.
First, a mine operator applying for a federal permit under the CWA must comply with CWA § 401, 33 U.S.C. § 1341 (2000), by providing the federal permitting agency with a certification from the proper state authority â in this case, WVDEPâ stating that any discharge from the mine site will comply with all applicable water quality standards. Next, the mine operator must obtain a National Pollutant Discharge Elimination System (âNPDESâ) permit pursuant to CWA § 402, 33 U.S.C. § 1342 (2000), if their project involves the discharge of a pollutant from a point source within the mining operation into navigable waters.
States wishing to administer their own NPDES program must be approved by the Environmental Protection Agency (âEPAâ) before they can begin issuing § 402 permits. 33 U.S.C. § 1342(c) (2000). West Virginia has had an EPA-approved § 402 program since 1982. See Approval of West Virginiaâs NPDES Program, 47 Fed. Reg. 22, 363 (May 24,1982).
Finally, and most importantly for the purposes of this litigation, surface mining projects that intend to dispose of excess spoil from their mining operations in jurisdictional waters must obtain a CWA § 404, 33 U.S.C. § 1344 (2000), permit from the Corps. Section 404 permits allow âthe discharge of dredged or fill material into the navigable waters at specified disposal sites.â 33 U.S.C.A. § 1344(a) (2008). The Corps uses § 404 permits to authorize the
In issuing § 404 permits, the Corps follows the § 404(b)(1) Guidelines (âCWA Guidelinesâ) promulgated by the Environmental Protection Agency (âEPAâ) pursuant to 33 U.S.C. § 1344(b)(1) (2008), and incorporated by the Corps into its own regulations. See 40 C.F.R. pt. 230 (2008); 33 C.F.R. § 320.2(f) (2008). The Guidelines prohibit discharges that âwill cause or contribute to significant degradation of the waters of the United States.â
The Corpsâ § 404 permit evaluation process must also include a public interest review component, in which â[t]he benefits which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments.â 33 C.F.R. § 320.4(a)(1) (2008). The Corpsâ decision to issue a permit âshould reflect the national concern for both protection and utilization of important resources.â Id. Ultimately, the § 404 permitting process requires extensive review and coordination with numerous federal and state agencies, as well as significant consideration of the public interest.
C.
Under NEPA, federal agencies must take a âhard lookâ at the potential environmental consequences of their actions. Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989). Because NEPA is a procedural and not a results-driven statute, even agency action with adverse environmental effects can be NEPA-compliant so long as the agency has considered those effects and determined that competing policy values outweigh those costs. Id.
NEPA requires only that federal agencies prepare an Environmental Impact Statement for âmajor Federal actions significantly affecting the quality of the human environment.â 42 U.S.C. § 4332(2)(C) (2000). Significance is determined by evaluating both the context of the action and the intensity, or severity, of the impact. 40 C.F.R. § 1508.27 (2008). Where it is not readily discernible how significant the environmental effects of a proposed action will be, federal agencies may prepare an Environmental Assessment (âEAâ). 40 C.F.R. § 1501.4(b) (2008). An EA is a âconcise public document ... that serves to ... [bjriefiy provide sufficient evidence and analysis for determining whether to prepare an [EIS] or a finding of no significant impact [(âFONSIâ)].â 40 C.F.R. § 1508.9(a)(1) (2008); see also 33 C.F.R. §§ 230.10-230.11 (2008) (explaining the Corpsâ requirements for an EA).
Even where an EA determines that a proposed action will have a significant environmental impact, an agency may
D.
Claims challenging federal agency action under the CWA and NEPA are subject to judicial review under the APA. 5 U.S.C. § 702 (2006); Holy Cross Wilderness Fund v. Madigan, 960 F.2d 1515, 1521 (10th Cir.1992). In issuing the § 404 permits challenged here, the Corps was engaged in informal (ânotice and commentâ) rule-making. 33 U.S.C. § 1344(a) (2000); Ohio Valley Envtl. Coal. v. Bulen, 429 F.3d 493, 496 (4th Cir.2005). Such informal rulemaking, done pursuant to Section 4 of the APA, 5 U.S.C. § 553 (2006), must be reviewed under Section 10 of the APA, 5 U.S.C. § 706(2) (2006). Ethyl Corp. v. EPA, 541 F.2d 1, 34 (D.C.Cir.1976).
Section 10 of the APA establishes that, as a general rule, âagency action, findings, and conclusionsâ will be set aside only when they are âfound to be ... arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.â 5 U.S.C. § 706(2) (2000); Citizens To Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 413-14, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971). Review under this standard is highly deferential, with a presumption in favor of finding the agency action valid. Natural Res. Def. Council, Inc. v. EPA 16 F.3d 1395, 1400 (4th Cir.1993). Especially in matters involving not just simple findings of fact but complex predictions based on special expertise, âa reviewing court must generally be at its most deferential.â Baltimore Gas & Elec. Co. v. Natural Res. Def. Council, 462 U.S. 87, 103, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983).
In determining whether agency action was arbitrary or capricious, the court must consider whether the agency considered the relevant factors and whether a clear error of judgment was made. Citizens To Preserve Overton Park, 401 U.S. at 416, 91 S.Ct. 814. âAlthough this inquiry into the facts is to be searching and careful, the ultimate standard of review is a narrow one. The court is not empowered to substitute its judgment for that of the agency.â Id. Deference is due where the agency has examined the relevant data and provided an explanation of its decision that includes âa ârational connection between the facts found and the choice made.â â Motor Vehicle Mfrs. Assân v. State Farm Mutual Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (quoting Burlington Truck Lines, Inc. v. United States, 371 U.S. 156, 168, 83 S.Ct. 239, 9 L.Ed.2d 207 (1962)); accord Ohio River Valley Envtl. Coal, Inc. v. Kempthorne, 473 F.3d 94, 102-03 (4th Cir.2006).
The âarbitrary and capriciousâ standard is not meant to reduce judicial review to a ârubber-stampâ of agency action. Ethyl Corp., 541 F.2d at 34. While the standard of review is narrow, the court must nonetheless engage in a âsearching and carefulâ inquiry of the record. Citizens To Preserve Overton Park, 401 U.S. at 416, 91 S.Ct. 814. But, this scrutiny of the record is meant primarily âto educate the courtâ so that it can âunderstand enough about the problem confronting the agency to comprehend the meaning of the evidence relied upon and the evidence discarded; the questions addressed by the agency and those bypassed; the choices
IV.
With this statutory guidance in mind, we turn now to the substance of this appeal, first taking up the issues on appeal concerning the district courtâs March 23, 2007, opinion and order.
A.
The Corps and Intervenors (collectively âAppellantsâ) claim on appeal that the Corpsâ decision about the scope of its NEPA analysis for each of these permits was entitled to deference as a reasonable interpretation of its own regulations. The district court found that the Corps acted contrary to its regulations by limiting the scope of its NEPA analysis to the impact of the filling of jurisdictional waters and by not looking at the larger environmental impacts of the valley fill as a whole. Agreeing with the district court, OVEC argues that the Corpsâ NEPA analysis should have considered all environmental impacts caused by the fill, including the impacts to the upland valleys where the fills will be located. The Corps counters that it reasonably determined that, under its regulations, its jurisdictional reach was limited to the affected waters and adjacent riparian areas and that this determination is entitled to deference.
Because we are asked here to review the Corpsâ interpretation of its own regulations, our review is cabined to assessing the reasonableness of that interpretation. This kind of review is highly deferential, with the agencyâs interpretation âcontrolling unless plainly erroneous or inconsistent with the regulation.â Auer v. Robbins, 519 U.S. 452, 461, 117 S.Ct. 905, 137 L.Ed.2d 79 (1997) (internal quotations omitted); see also Bowles v. Seminole Rock & Sand Co., 325 U.S. 410, 413-14, 65 S.Ct. 1215, 89 L.Ed. 1700 (1945); Kentuckians for the Commonwealth v. Rivenburgh, 317 F.3d 425, 439 (4th Cir.2003) (noting that, when reviewing an agencyâs interpretation of its own regulation, â[t]he reviewing court does not have much leewayâ). In applying this principle, also known as âAuer deferenceâ or âSeminole Rock deference,â we must first determine whether the regulation itself is unambiguous; if so, its plain language controls. See Christensen v. Harris County, 529 U.S. 576, 588, 120 S.Ct. 1655, 146 L.Ed.2d 621 (2000); United States v. Deaton, 332 F.3d 698, 709 (4th Cir.2003). If ambiguous,
NEPA requires federal agencies to take a âhard lookâ at the environmental consequences of their actions, but the statute does not specify how an agency should determine the scope of its NEPA analysis. Wetlands Action Network v. United States Army Corps of Engârs, 222 F.3d 1105, 1115 (9th Cir.2000). The Corpsâ implementing regulations, however, specify that the proper scope of analysis for NEPA review is âto address the impacts of the specific activity requiring a DA [Department of the Army] permit and those portions of the entire project over which the [Corps] district engineer has sufficient control and responsibility to warrant Federal review.â 33 C.F.R. pt. 325, App. B, § 7(b)(1) (2008). OVECâs challenge to the scope of the Corpsâ NEPA review rests largely on its misapprehension of what constitutes the âspecific activityâ requiring a permit.
The Corpsâ regulations are unambiguous in requiring a district engineer to address the impacts of the âspecific activity requiring a DA [Department of the Army] permitâ in its NEPA analysis. Id. According to OVEC, the Corpsâ § 404 permit is a permit for the entire valley fill, down to the last shovelful of dirt at the edge of the valley. But § 404 is itself unambiguous about what the Corps is authorized to permit under the CWA: the Corps âmay issue permits, after notice and opportunity for public hearings for the discharge of dredged or fill material into the navigable waters at specified disposal sites.â 33 U.S.C. § 1344(a) (2000) (emphasis added). The specific activity that the Corps is permitting when it issues a § 404 permit is nothing more than the filling of jurisdictional waters for the purpose of creating an underdrain system for the larger valley fill. In fact, the Corps has no legal authority to prevent the placement of fill material in areas outside of the waters of the United States. All other fill activity falls under the exclusive jurisdiction of the WVDEP, as the federally approved state SMCRA regulatory authority.
Of course, even if the âspecific activityâ being permitted under CWA § 404 is the filling of valley streams, the Corps could still be required under NEPA to consider larger impacts of the broader valley fill project if the Corps is found to have âsufficient control and responsibility to warrant Federal review.â 33 C.F.R. pt. 325, App. B, § 7(b)(1) (2008). In eases where the permitted activity is only one part of a larger project, the regulations specify that the Corps has âcontrol and responsibility for portions of the project beyond the limits of Corps jurisdiction where the Federal involvement is sufficient to turn an essentially private action into a Federal action. These are eases where the environmental consequences of the larger project are essentially products of the Corps permit action.â 33 C.F.R. pt. 325, App. B, § 7(b)(2) (2008) (emphasis added).
The regulations go on to suggest several factors to be considered in making this determination, including:
(i) Whether or not the regulated activity comprises âmerely a linkâ in a corridor type project (e.g., a transportation or utility transmission project).
(ii) Whether there are aspects of the upland facility in the immediate vicinity of the regulated activity which affect the location and configuration of the regulated activity.
(iii) The extent to which the entire project will be within Corps jurisdiction.
(iv) The extent of cumulative Federal control and responsibility.
Id.
OVECâs argument that the Corps has sufficient control and responsibility over
The Corpsâ jurisdiction under CWA § 404 is limited to the narrow issue of the filling of jurisdictional waters. To say that the Corps has a level of control and responsibility over the entire valley fill project such that âthe environmental consequences of the larger project are essentially products of the Corps permit action,â 33 C.F.R. pt. 325, App. B, § 7(b)(2) (2008), is to effectively read out of the equation the elaborate, congressionally mandated schema for the permitting of surface mining operations prescribed by SMCRA.
Under SMCRA, the state of West Virginia has âexclusive jurisdiction over the regulation of surface coal mining and reclamation operations.â 30 U.S.C. § 1253 (2000). Congress clearly contemplated that the regulation of the disposal of excess spoil and the creation of valley fills fall under the SMCRA rubric. See 30 U.S.C. § 1265(b)(22)(D) (2000) (requiring that lateral drains be constructed where a spoil disposal area contains âsprings, natural water courses or wet weather seepsâ); Kentuckians for the Commonwealth, Inc. v. Rivenburgh, 317 F.3d 425, 443 (4th Cir.2003) (â[I]t is beyond dispute that SMCRA recognizes the possibility of placing excess spoil material in waters of the United States.... â).
As part of its federally approved SMCRA regulatory program, the WVDEP surface mine permitting process examines â[ejvery detail of the manner in which a coal mining operation is to be conducted .... including] the plan for disposal of excess spoil for surface ... mining opera-tions_â (Br. for the W. Va. Depât of Commerce and the W. Va. Depât of Envtl. Prot. as Amici Curiae Supporting Appellants at 13.) As the Corps explains in its permits, âthe social and environmental impacts associated with surface coal mining and reclamation operations are appropriately analyzed by WVDEP in this context before that agency decides whether to permit the mining operation under SMCRA.â Camp Branch CDD 4; Black Castle CDD 6; Laxare East CDD 7; United States Army Corps of Engineers, Combined Decision Document for the Republic No. 2
If the Corps, by issuing a § 404 permit, can turn a valley fill project âinto a Federal action,â 33 C.F.R. pt. 325, App. B, § 7(b)(2) (2008), the WVDEPâs regulation of the fill process becomes at best duplica-tive, and, at worst, meaningless. NEPA plainly is not intended to require duplication of work by state and federal agencies. See 40 C.F.R. § 1506.2(b) (âAgencies shall cooperate with State and local agencies to the fullest extent possible to reduce duplication between NEPA and State and local requirements....â). The Corpsâ general regulatory approach echoes this sentiment. See 33 C.F.R. § 320.1(a)(5) (2008) (âThe Corps believes that state and federal regulatory programs should complement rather than duplicate one another.â); 33 C.F.R. § 337.1 (2008) (noting that, in issuing public notice for projects involving the discharge of fill material into jurisdictional waters, â[district engineers are encouraged to develop procedures to avoid unnecessary duplication of state agency proceduresâ).
SMCRA also calls for a coordinated and non-duplicative approach to environmental review. See 30 U.S.C. § 1253(a)(6) (2000) (requiring that a state SMCRA program establish âfor the purposes of avoiding duplication, ... a process for coordinating the review and issuance of permits for surface coal mining and reclamation operations with any other Federal or State permit process applicable to the proposed operationsâ). While SMCRAâs provisions should not be construed as âsuperseding, amending, modifying, or repealingâ the requirements of NEPA or the CWA, 30 U.S.C. § 1292(a) (2000), neither should NEPA be construed to require the Corps to essentially federalize an environmental review process that has already been delegated to federally approved state programs. See Wetlands Action Network, 222 F.3d at 1117 (noting, in support of its finding that the Corpsâ NEPA analysis for a wetlands-filling permit need not include the effects of the larger development project, that state regulations control the design of the project and that the larger project was already subject to extensive state environmental review); Sylvester v. U.S. Army Corps of Engârs, 884 F.2d 394, 401 (9th Cir.1989) (âWe, finally, draw comfort from the fact that ordinary notions of efficiency suggest a federal environmental review should not duplicate competently performed state environmental analyses.â).
In Department of Transportation v. Public Citizen,