Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. 1 of Snohomish Cty.
AI Case Brief
Generate an AI-powered case brief with:
Estimated cost: $0.001 - $0.003 per brief
Full Opinion
delivered the opinion of the Court.
Under the Mobile-Sierra doctrine, the Federal Energy Regulatory Commission (FERC or Commission) must presume that the rate set out in a freely negotiated wholesale-energy contract meets the âjust and reasonableâ requirement imposed by law. The presumption may be overcome only if FERC concludes that the contract seriously harms the public interest. These cases present two questions
I
A
Statutory Background
The Federal Power Act (FPA), 41 Stat. 1063, as amended, gives the Commission
The FPA requires all wholesale-electricity rates to be âjust and reasonable.â § 824d(a). When a utility files a new
The statutory requirement that rates be âjust and reasonableâ is obviously incapable of precise judicial definition, and we afford great deference to the Commission in its rate decisions. See FPC v. Texaco Inc., 417 U. S. 380, 389 (1974); Permian Basin Area Rate Cases, 390 U. S. 747, 767 (1968). We have repeatedly emphasized that the Commission is not bound to any one ratemaking formula. See Mobil Oil Exploration & Producing Southeast, Inc. v. United Distribution Cos., 498 U. S. 211, 224 (1991); Permian Basin, supra, at 776-777. But FERC must choose a method that entails an appropriate âbalancing of the investor and the consumer interests.â FPC v. Hope Natural Gas Co., 320 U. S. 591, 603 (1944). In exercising its broad discretion, the Commission traditionally reviewed and set tariff rates under the âcost-of-serviceâ method, which ensures that a seller of electricity recovers its' costs plus a rate of return sufficient to attract necessary capital. See J. McGrew, Federal Energy Regulatory Commission 152, 160-161 (2003) (hereinafter McGrew).
In two cases decided on the same day in 1956, we addressed the authority of the Commission to modify rates set bilaterally by contract rather than unilaterally by tariff. In United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U. S. 332, we rejected a natural-gas utilityâs argument that
In FPC v. Sierra Pacific Power Co., 350 U. S. 348, 352-353 (1956), we applied the holding of Mobile to the analogous provisions of the FPA, concluding that the complaining utility could not supersede a contract rate simply by filing a new tariff. In Sierra, however, the Commission had concluded not only (contrary to our holding) that the newly filed tariff superseded the contract, but also that the contract rate itself was not just and reasonable, âsolely because it yield[ed] less than a fair return on the net invested capitalâ of the utility. 350 U. S., at 355. Thus, we were confronted with the question of how the Commission may evaluate whether a contract rate is just and reasonable.
We answered that question in the following way:
â[T]he Commissionâs conclusion appears on its face to be based on an erroneous standard. . . . [W]hile it may be that the Commission may not normally impose upon a public utility a rate which would produce less than a fair return, it does not follow that the public utility may not itself agree by contract to a rate affording less than a fair return or that, if it does so, it is entitled to be relieved of its improvident bargain. ... In such circumstances the sole concern of the Commission would seem to be whether the rate is so low as to adversely affect the public interest â as where it might impair the financial ability of the public utility to continue its service, cast upon other consumers an excessive burden, or be unduly discriminatory.â Id., at 354-355 (emphasis deleted).
Over the past 50 years, decisions of this Court and the Courts of Appeals have refined the Mobile-Sierra presumption to allow greater freedom of contract. In United Gas Pipe Line Co. v. Memphis Light, Gas and Water Div., 358 U. S. 103, 110-113 (1958), we held that parties could contract out of the Mobile-Sierra presumption by specifying in their contracts that a new rate filed with the Commission would supersede the contract rate. Courts of Appeals have held that contracting parties may also agree to a middle option between Mobile-Sierra and Memphis Light: A contract that does not allow the seller to supersede the contract rate by filing a new rate may nonetheless permit the Commission to set aside the contract rate if it results in an unfair rate of return, not just if it violates the public interest. See, e. g., Papago Tribal Util. Auth. v. FERC, 723 F. 2d 950, 953 (CADC 1983); Louisiana Power & Light Co. v. FERC, 587 F. 2d 671, 675-676 (CA5 1979). Thus, as the Mobile-Sierra doctrine has developed, regulated parties have retained broad authority to specify whether FERC can review a contract rate solely for whether it violates the public interest or also for whether it results in an unfair rate of return. But the Mobile-Sierra presumption remains the default rule.
Moreover, even though the challenges in Mobile and Sierra were brought by sellers, lower courts have concluded that the Mobile-Sierra presumption also applies where a purchaser, rather than a seller, asks FERC to modify a contract. See Potomac Elec. Power Co. v. FERC, 210 F. 3d 403, 404-405, 409-410 (CADC 2000); Boston Edison Co. v. FERC, 856 F. 2d 361, 372 (CA1 1988). This Court has seemingly blessed that conclusion, explaining that under the FPA, â[w]hen commercial parties . . . avail themselves of rate
Over the years, the Commission began to refer to the two modes of reviewâone with the Mobile-Sierra presumption and the other withoutâas the âpublic interest standardâ and the âjust and reasonable standard.â See, e. g., In re Southern Company Servs., Inc., 39 FERC ¶ 63,026, pp. 65,134, 65,141 (1987). Decisions from the Courts of Appeals did likewise. See, e. g., Kansas Cities v. FERC, 723 F. 2d 82, 87-88 (CADC 1983); Northeast Utils. Serv. Co. v. FERC, 993 F. 2d 937, 961 (CA1 1993). We do not take this nomenclature to stand for the obviously indefensible proposition that a standard different from the statutory just-and-reasonable standard applies to contract rates. Rather, the term âpublic interest standardâ refers to the differing application of that just-and-reasonable standard to contract rates. See Philadelphia Elec. Co., 58 F. R C. 88, 90 (1977). (It would be less confusing to adopt the Solicitor Generalâs terminology, referring to the two differing applications of the just-and-reasonable standard as the âordinaryâ âjust and reasonable standardâ and the âpublic interest standard.â See Reply Brief for Respondent FERC 6.)
B
Recent FERC Innovations; Market-Based Tariffs
In recent decades, the Commission has undertaken an ambitious program of market-based reforms. Part of the impetus for those changes was technological evolution. Historically, electric utilities had been vertically integrated monopolies. For a particular geographic area, a single utility would control the generation of electricity, its transmission, and its distribution to consumers. See Midwest ISO Transmission Owners v. FERC, 373 F. 3d 1361, 1363 (CADC 2004). Since the 1970âs, however, engineering innovations have lowered the cost of generating electricity and transmit
To take advantage of these changes, the Commission has attempted to break down regulatory and economic barriers that hinder a free market in wholesale electricity. It has sought to promote competition in those areas of the industry amenable to competition, such as the segment that generates electric power, while ensuring that the segment of the industry characterized by natural monopoly â namely, the transmission grid that conveys the generated electricity â cannot exert monopolistic influence over other areas. See New York, supra, at 9-10; Snohomish, supra. To that end, FERC required in Order No. 888 that each transmission provider offer transmission service to all customers on an equal basis by filing an âopen access transmission tariff.â Promoting Wholesale Competition Through Open Access NonDiscriminatory Transmission Services by Public Utilities, 61 Fed. Reg. 21540 (1996); see New York, supra, at 10-12. That requirement prevents the utilities that own the grid from offering more favorable transmission terms to their own affiliates and thereby extending their monopoly power to other areas of the industry.
To further pry open the wholesale-electricity market and to reduce technical inefficiencies caused when different utilities operate different portions of the grid independently, the Commission has encouraged transmission providers to establish âRegional Transmission Organizationsâ â entities to which transmission providers would transfer operational control of their facilities for the purpose of efficient coordination. Order No. 2000, 65 Fed. Reg. 810, 811-812 (2000); see Midwest ISO, supra, at 1364. It has encouraged the management of those entities by âIndependent System Operators,â not-for-profit entities that operate transmission facili
Against this backdrop of technological change and market-based reforms, the Commission over the past two decades has begun to permit sellers of wholesale electricity to file âmarket-basedâ tariffs. These tariffs, instead of setting forth rate schedules or rate-fixing contracts, simply state that the seller will enter into freely negotiated contracts with purchasers. See generally Market-Based Rates for Wholesale Sales of Electric Energy, Capacity and Ancillary Services by Public Utilities, Order No. 697, 72 Fed. Reg. 39904 (2007) (hereinafter Market-Based Rates); McGrew 160-167. FERC does not subject the contracts entered into under these tariffs (as it subjected traditional wholesale-power contracts) to § 824dâs requirement of immediate filing, apparently on the theory that the requirement has been satisfied by the initial filing of the market-based tariffs themselves. See Brief for Respondent FERC 28-29 (hereinafter Brief for FERC).
FERC will grant approval of a market-based tariff only if a utility demonstrates that it lacks or has adequately mitigated market power, lacks the capacity to erect other barriers to entry, and has avoided giving preferences to its affiliates. See Market-Based Rates ¶ 7, 72 Fed. Reg. 39907. In addition to the initial authorization of a market-based tariff, FERC imposes ongoing reporting requirements. A seller must file quarterly reports summarizing the contracts that it has entered into, even extremely short-term contracts. See California ex rel. Lockyer v. FERC, 383 F. 3d 1006, 1013 (CA9 2004). It must also demonstrate every four months
Both the Ninth Circuit and the D. C. Circuit have generally approved FERCâs scheme of market-based tariffs. See Lockyer, supra, at 1011-1013; Louisiana Energy & Power Auth. v. FERC, 141 F. 3d 364, 365 (CADC 1998). We have not hitherto approved, and express no opinion today, on the lawfulness of the market-based-tariff system, which is not one of the issues before us. It suffices for the present cases to recognize that when a seller files a market-based tariff, purchasers no longer have the option of buying electricity at a rate set by tariff and contracts no longer need to be filed with FERC (and subjected to its investigatory power) before going into effect.
C
Californiaâs Electricity Regulation and Its Consequences
In 1996, California enacted Assembly Bill 1890 (AB 1890), which massively restructured the California electricity market. See 1996 Cal. Stat. ch. 854 (codified at Cal. Pub. Util. Code Ann. §§ 330-398.5 (West 2004 and Supp. 2008)); see generally Cudahy, Whither Deregulation: A Look at the Portents, 58 N. Y. U. Annual Survey of Am. Law 155, 172-185 (2001) (hereinafter Cudahy). The bill transferred operational control of the transmission facilities of Californiaâs three largest investor-owned utilities to an Independent Service Operator (Cal-ISO). See Pacific Gas & Elec. Co. v.
In 1997, FERC approved the Cal-ISO as consistent with the requirements for an Independent Service Operator established in Order No. 888. FERC also approved the CalPX and the investor-owned utilitiesâ authority to make sales at market-based rates in the CalPX, finding that, in light of the divesture of their generation units and other conditions imposed under the restructuring plan, those utilities had adequately mitigated their market power. See Pacific Gas & Elec. Co., 81 FERC ¶ 61,122, pp. 61,435, 61,435-61,436, 61,537-61,548 (1997).
The CalPX opened for business in March 1998. In the summer of 1999, it expanded to include an auction for sales of electricity under âforward contractsââcontracts in which sellers promise to deliver electricity more than one day in the future (sometimes many years). But the participation of Californiaâs large investor-owned utilities in that forward market was limited because, as we have said, AB 1890 strictly capped the amount of power that they could purchase outside of the spot market. See 471 F. 3d, at 1068.
That diminishment of the role of long-term contracts in the California electricity market turned out to be one of the seeds of an energy crisis. In the summer of 2000, the price of electricity in the CalPXâs spot market jumped dramatically â more than fifteenfold. See ibid. The increase was the result of a combination of natural, economic, and regula
In late 2000, the Commission took action. A central plank of its emergency effort was to eliminate the utilitiesâ reliance on the CalPXâs spot market and to shift their purchases to the forward market. To that end, FERC abolished the requirement that investor-owned utilities purchase and sell all power through the CalPX and encouraged them to enter into long-term contracts. See San Diego Gas & Electric Co. v. Sellers of Energy and Ancillary Servs., 93 FERC ¶ 61,294, pp. 61,980, 61,982 (2000); see also 471 F. 3d, at 1069. The Commission also put price caps on wholesale electricity. See San Diego Gas & Elec. Co. v. Sellers of Energy and Ancillary Servs., 95 FERC ¶ 61,418, p. 62,545 (2001). By June 2001, electricity prices began to decline to normal levels. Id., at 62,546.
D
Genesis of These Cases
The principal respondents in these cases are western utilities that purchased power under long-term contracts during that tumultuous period in 2000 and 2001. Although they are not located in California, the high prices in California spilled
The contracts between the parties included rates that were very high by historical standards. For example, respondent Snohomish signed a 9-year contract to purchase electricity from petitioner Morgan Stanley at a rate of $105/ megawatt hour (MWh), whereas prices in the Pacific Northwest have historically averaged $24/MWh. The contract prices were substantially lower, however, than the prices that Snohomish would have paid in the spot market during the energy crisis, when prices peaked at $3,300/MWh. See id., at 1069-1070.
After the crisis had passed, buyerâs remorse set in and respondents asked FERC to modify the contracts. They contended that the rates in the contracts should not be presumed to be just and reasonable under Mobile-Sierra because, given the sellersâ market-based tariffs, the contracts had never been initially approved by the Commission without the presumption. See Nevada Power Co. v. Enron Power Marketing, Inc., 103 FERC ¶ 61,353, pp. 62,382, 62,387 (2003). Respondents also argued that contract modification was warranted even under the Mobile-Sierra presumption because the contract rates were so high that they violated the public interest. See 103 FERC, at 62,383, 62,387-62,395.
In a preliminary order, the Commission instructed the Administrative Law Judge (ALJ) to consider 12 different factors in deciding whether the presumption could be overcome for the contracts, such as the terms of the contracts, the available alternatives at the time of sale, the relationship of the rates to Commission benchmarks, the effect of the contracts on the financial health of the purchasers, and the impact of contract modification on national energy markets. After a hearing, the ALJ concluded that the Mobile-Sierra presumption should apply to the contracts and that the con
Between the ALJâs decision and the Commissionâs ruling, the Commissionâs staff issued a report (Staff Report) concluding that unlawful activities of various sellers in the spot market had affected prices in the forward market. See id., at 62,396. Respondents raised the report at oral argument before the Commission, and some of them argued that petitioners âwere unlawfully manipulating market prices, thereby engaging in fraud and deception in violation of their market-based rate tariffs.â Ibid. Petitioners contended, however, that the Staff Report demonstrated only a correlation between rates in the spot and forward markets, not a causal connection. See ibid.
FERC affirmed the ALJ. The Commission first held that the Mobile-Sierra presumption did apply to the contracts at issue. Although agreeing with respondents that the presumption applies only where FERC has had an initial opportunity to review a contract rate, the Commission relied on the somewhat metaphysical ground that the grant of market-based authority to petitioners qualified as that initial opportunity. See 103 FERC, at 62,388-62,389. The Commission then held that respondents could not overcome the Mobile-Sierra presumption. It recognized that the Staff Report had âfound that spot market distortions flowed through to forward power prices,â 103 FERC, at 62,396-62,397, but concluded that this finding, even if true, was not âdeterminativeâ because:
âa finding that the unjust and unreasonable spot market caused forward bilateral prices to be unjust and unreasonable would be relevant to contract modification only where there is a âjust and reasonableâ standard of review. . . . Under the âpublic interestâ standard, to jus*543 tify contract modification it is not enough to show that forward prices became unjust and unreasonable due to the impact of spot market dysfunctions; it must be shown that the rates, terms and conditions are contrary to the public interest.â Id., at 62,397.
The Commission determined that under the factors identified in Sierra, as well as under a totality-of-the-circumstances test, respondents had not demonstrated that the contracts threatened the public interest. See 103 FERC, at 62,397-62,399. On rehearing, respondents reiterated their complaints, including their charge that âtheir contracts were the product of market manipulation by Enron, Morgan Stanley and other [sellers].â 105 FERC ¶ 61,185, pp. 61,979, 61,989 (2003). The Commission answered that there was âno evidence to support a finding of market manipulation that specifically affected the contracts at issue.â Id., at 61,989.
Respondents filed petitions for review in the Ninth Circuit, which granted the petitions and remanded to the Commission, finding two flaws in the Commissionâs analysis.
We granted certiorari. See 551 U. S. 1189 (2007).
II
A
Application of Mobile-Sierra Presumption to Contracts Concluded Under Market-Based Rate Authority
As noted earlier, the FERC order under review here agreed with the Ninth Circuitâs premise that the Commission must have an initial opportunity to review a contract without the Mobile-Sierra presumption, but maintained that the authorization for market-based rate authority qualified as that initial review. Before this Court, however, FERC changes its tune, arguing that there is no such prerequisite â or at least that FERC could reasonably conclude so and therefore that Chevron deference is in order. See Brief for FERC 20-21, 33-34; Chevron U. S. A. Inc. v. Natural Resources Defense Council, Inc., 467 U. S. 837 (1984). We will not uphold a discretionary agency decision where the agency has offered a justification in court different from what it provided in its opinion. See SEC v. Chenery Corp., 318 U. S. 80, 94-95 (1943). But FERC has lucked out: The Chenery doctrine has no application to these cases, because we conclude that the Commission was required, under our decision in Sierra,
We are in broad agreement with the Ninth Circuit on a central premise: There is only one statutory standard for assessing wholesale-electricity rates, whether set by contract or tariff â the just-and-reasonable standard. The plain text of the FPA states that â[a]ll rates . . . shall be just and reasonable.â 16 U. S. C. § 824d(a); see also § 824e(a) (2000 ed., Supp. V). But we disagree with the Ninth Circuitâs interpretation of Sierra as requiring (contrary to the statute) that the Commission apply the standard differently, depending on when a contract rate is challenged. In the Ninth Circuitâs view, Sierra was premised on the idea that âas long as the rate was just and reasonable when the contract was formed, there would be a presumption . . . that the reasonableness continued throughout the term of the contract.â 471 F. 3d, at 1077. In other words, so long as the Commission concludes (either after a hearing or by allowing a rate to go into effect) that a contract rate is just and reasonable when initially filed, the rate will be presumed just and reasonable in future proceedings.
That is a misreading of Sierra. Sierra was grounded in the commonsense notion that â[i]n wholesale markets, the party charging the rate and the party charged [are] often sophisticated businesses enjoying presumptively equal bargaining power, who could be expected to negotiate a âjust and reasonableâ rate as between the two of them.â Verizon, 535 U. S., at 479. Therefore, only when the mutually agreed-upon contract rate seriously harms the consuming
The Ninth Circuit found support for its prerequisite in our decision in FPC v. Texaco Inc., 417 U. S. 380 (1974). In that case, we warned that the Commissionâs attempt to rely solely on market forces to evaluate rates charged by small natural-gas producers was inconsistent with the Natural Gas Actâs insistence that rates be just and reasonable. See id., at 397. The Ninth Circuit apparently took this to mean that all initially filed contracts must be subject to review without the Mobile-Sierra presumption. But Texaco had nothing to do with that doctrine. It held that the Commission had improperly implemented a scheme of total deregulation by applying no standard of review at all to small-producer rates. See 417 U. S., at 395-397. It did not cast doubt on the proposition that in a proper regulatory scheme, the ordinary mode for evaluating contractually set rates is to look to
Nor do we agree with the Ninth Circuit that FERC must inquire into whether a contract was formed in an environment of market âdysfunctionâ before applying the Mobile-Sierra presumption. Markets are not perfect, and one of the reasons that parties enter into wholesale-power contracts is precisely to hedge against the volatility that market imperfections produce. That is why one of the Commissionâs responses to the energy crisis was to remove regulatory barriers to long-term contracts. It would be a perverse rule that rendered contracts less likely to be enforced when there is volatility in the market. (Such a rule would come into play, after all, only when a contract formed in a period of âdysfunctionâ did not significantly harm the consuming public, since contracts that seriously harm the public should be set aside even under the Mobile-Sierra presumption.) By enabling sophisticated parties who weathered market turmoil by entering long-term contracts to renounce those contracts once the storm has passed, the Ninth Circuitâs holding would reduce the incentive to conclude such contracts in the future. Such a rule has no support in our case law and plainly undermines the role of contracts in the FPAâs statutory scheme.
To be sure, FERC has ample authority to set aside a contract where there is unfair dealing at the contract formation stage â for instance, if it finds traditional grounds for the abrogation of the contract such as fraud or duress. See 103 FERC, at 62,399-62,400 (â[T]here is no evidence of unfairness, bad faith, or duress in the original negotiationsâ). In addition, if the âdysfunctionalâ market conditions under which the contract was formed were caused by illegal action of one of the parties, FERC should not apply the Mobile-Sierra presumption. See Part III, infra. But the mere
We reiterate that we do not address the lawfulness of FERCâs market-based-rates scheme, which assuredly has its critics. But any needed revision in that scheme is properly addressed in a challenge to the scheme itself, not through a disfigurement of the venerable Mobile-Sierra doctrine. We hold only that FERC may abrogate a valid contract only if it harms the public interest.
B
Application of âExcessive Burdenâ Exception to High-Rate Challenges
We turn now to the Ninth Circuitâs second holding: that a âzone of reasonablenessâ test should be used to evaluate a buyerâs challenge that a rate is too high. In our view that fails to accord an adequate level of protection to contracts. The standard for a buyerâs challenge must be the same, generally speaking, as the standard for a sellerâs challenge: The contract rate must seriously harm the public interest. That is the standard that the Commission applied in the proceedings below.