AI Case Brief
Generate an AI-powered case brief with:
Estimated cost: $0.001 - $0.003 per brief
Full Opinion
Opinion by Judge W. FLETCHER; Partial Concurrence and Partial Dissent by Judge RAWLINSON.
OPINION
The Bureau of Ocean Energy Management (âBOEMâ)
Plaintiffs argued in the district court that BOEM abused its discretion by failing to account for essential missing information in the FEIS. Plaintiffs also argued that BOEMâs estimate of one billion barrels is arbitrary and capricious. They contended that the potential economically recoverable oil from the lease sale is far higher than one billion barrels, and that BOEM had not given an adequate explanation for using its lower estimate. The district court initially rejected the FEIS for failing to account for the missing information. After remand, BOEM prepared a Supplemental EIS (âSEISâ) addressing the missing information. Based on the FEIS and SEIS, the district court granted summary judgment to defendants.
We largely agree with the district court that the agency did not abuse its discretion in its analysis of the missing information. However, we agree with plaintiffs that the agencyâs estimate of one billion barrels was chosen arbitrarily, and that this arbitrary decision meant that the agency based its decision on inadequate information about the amount of oil to be produced pursuant to the lease sale.
I. Background
The Chukchi Sea is a southern arm of the Arctic Ocean between Alaska and Russia. The Sea contains a wide variety of animals, including bowhead whales, polar bears, pacific walrus, seals, fish, and birds. Some of these animals provide subsistence for native Inupiat communities along the Alaskan coast. Some of the animals are listed under the Endangered Species Act (âESAâ) as endangered or threatened. Five exploratory wells were drilled in the Sea between 1989 and 1991. They had âpositive showsâ but did not lead to commercial production.
A. NEPA
NEPA âprotects] the environment by requiring that federal agencies carefully weigh environmental considerations and consider potential alternatives to the proposed action before the government launches any major federal action.â Barnes v. U.S. Depât of Transp., 655 F.3d 1124, 1131 (9th Cir.2011) (internal quotation marks omitted). â âNEPA imposes procedural requirements designed to force agencies to take a âhard lookâ at environmental consequencesâ â of major federal action. Id. (quoting Earth Island Inst. v. U.S. Forest Serv., 351 F.3d 1291, 1300 (9th Cir.2003)). The statute requires federal agencies to âconsider every significant aspect of the environmental impact of a proposed actionâ and to âinform the public that [they] ha[ve] indeed considered environmental concerns in [their] decisionmak-ing process.â Balt. Gas & Elec. Co. v. Natural Res. Def. Council, Inc., 462 U.S. 87, 97, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983) (internal quotation marks omitted).
NEPA requires that federal agencies prepare an EIS for any âmajor Federal actions significantly affecting the quality of the human environment.â 42 U.S.C. § 4332(2)(C). An agency must consider:
(i) the environmental impact of the proposed action,
(ii) any adverse environmental effects which cannot be avoided should the proposal be implemented,
(iii) alternatives to the proposed action,
(iv) the relationship between local short-term uses of manâs environment and the maintenance and enhancement of long-term productivity, and
(v) any irreversible and irretrievable commitments of resources which would be involved in the proposed action should it be implemented.
Id. An agency must take into account all âreasonably foreseeable significant adverse effectsâ of the proposed action in its analysis of environmental effects. 40 C.F.R. § 1502.22; see also id. § 1508.7. NEPA also requires an agency to analyze missing and incomplete information. As we explain in greater detail below, an agency must either obtain information that is âessential to a reasoned choice among alternativesâ or explain why such information was too costly or difficult to obtain. Id. § 1502.22.
An agency is required to comply with NEPA at various stages of the oil and gas development process. An agency is not required at the lease sale stage to
B. Lease Sale 193
After completing a five-year leasing plan for the Chukchi Sea, BOEM decided to offer a large portion of the Sea for oil and gas leasing. The FEIS analyzed four alternatives for the lease sale: (1) a 34-million acre proposed lease option covering 6,156 blocks of the Chukchi Sea; (2) a no-lease option; (3) a proposed lease option excluding 1,765 blocks extending along a corridor about 60 miles from the Alaskan coast; and (4) a proposed lease option excluding 795 blocks extending along a corridor between 25 and 50 miles from the Alaskan coast.
The National Marine Fisheries Service recommended that the Secretary of the Interior select the third alternative, under which development would be farther from the coast, based on its conclusion that numerous endangered and threatened species living close to shore would be adversely affected by oil development. The Secretary of the Interior accepted BOEMâs recommendation and selected the fourth alternative, under which development would be closer to the coast.
The lease sale occurred on February 6, 2008. The federal government collected over $2.6 billion from the winning bidders. At the time of the lease sale, there were no active leases in the Sea.
C. Procedural History
Plaintiffs filed suit, alleging seven deficiencies in the FEIS:
1. [The FEIS] does not adequately analyze and present the impacts of Lease Sale 193 on the environment and human communities;
2. [It] fails to include essential missing information about the Chukchi Sea and the potential impacts of the lease sale, or explain why excluding this information is justified;
3. [It] fails to adequately analyze the impact of the lease sale in the context of a warming climate;
4. [It] understates the potential impacts of oil and gas development pursuant to the leases by analyzing a limited development scenario;
5. [It] understates the risks of an oil spill;
6. [It] fails to fully analyze the cumulative impacts to threatened eiders of the lease sale and other oil and gas development in threatened eidersâ Arctic habitat; and
7. [It] provides a misleading analysis of the effects of seismic surveying.
The parties cross-moved for summary judgment.
The district court agreed with defendants that much of the FEIS complied with NEPA, including the FEISâs assumption that there would be one billion barrels of economically recoverable oil. However, the court concluded that the FEISâs analysis was flawed in three respects: it âfailed
After remand from the district court, BOEM prepared an SEIS. The SEIS analyzed the consequences of natural gas exploration and production. In the aftermath of the Deepwater Horizon oil spill in the Gulf Coast, it also analyzed the environmental impacts of a very large oil spill. Finally, BOEM prepared an appendix analyzing âwhether the information gaps that were identified in the Sale 193 FEIS were relevant and necessary to evaluate reasonably foreseeable significant adverse effects.â Based on the FEIS, now supplemented by the SEIS, the Secretary of Interior again chose the fourth alternative for oil and gas leasing.
Based on the FEIS and SEIS, the district court granted BOEMâs motion for summary judgment. The court found that âBOEM has identified missing or incomplete information and has adequately evaluated it in a manner that is clearly sufficient at this stage of the development process to satisfy the requirements of 40 C.F.R. § 1502.22.â The court gave âconsiderable deference ... to BOEMâs expertise.â Plaintiffs timely appealed.
II. Standard of Review
Our review of an EIS is governed by the Administrative Procedure Act (âAPAâ). âUnder the APA, we may set aside an agency decision if it is âarbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.â â Native Ecosystems Council v. U.S. Forest Serv., 428 F.3d 1233, 1238 (9th Cir.2005) (quoting 5 U.S.C. § 706(2)(A)). âReview under the arbitrary and capricious standard is narrow, and we do not substitute our judgment for that of the agency.â Lands Council v. McNair (Lands Council II), 537 F.3d 981, 987 (9th Cir.2008) (en banc) (alterations and internal quotation marks omitted). However, an agencyâs decision can be set aside if:
the agency relied on factors Congress did not intend it to consider, entirely failed to consider an important aspect of the problem, or offered an explanation that runs counter to the evidence before the agency or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise.
Id. (internal quotation marks omitted). Such actions would be âclear error[s] of judgment that would render [the agencyâs] action arbitrary and capricious.â Id. at 993 (internal quotation marks omitted).
We âmay affirm a summary judgment only if, viewing the evidence in the light most favorable to the party against whom it is granted, we find no genuine issue of material fact, and we find that the prevailing party is clearly entitled to judgment as a matter of law.â California v. Watt, 683 F.2d 1253, 1258 (9th Cir.1982), revâd on other grounds sub nom. Secây of the Interior v. California, 464 U.S. 312, 104 S.Ct. 656, 78 L.Ed.2d 496 (1984).
III. Discussion
On appeal, plaintiffs argue that BOEM abused its discretion in two respects. First, they argue that âessentialâ information is missing from the FEIS and SEIS, in violation of 40 C.F.R. § 1502.22. Second, they argue that the FEIS and SEIS un
A. Essential Information
An agencyâs obligation with respect to incomplete or unavailable information is spelled out in 40 C.F.R. § 1502.22. The agency âshall always make clear that ... information is lacking.â Id. If the missing information is ârelevant to reasonably foreseeable significant adverse impactsâ and is âessential to a reasoned choice among alternatives and the overall costs of obtaining it are not exorbitant,â the agency must include that information in the EIS. Id. § 1502.22(a). If the missing information âcannot be obtained because the overall costs of obtaining it are exorbitant or the means to obtain it are not known,â the agency must include the following in the EIS: (1) a statement that such information is âincomplete or unavailableâ; (2) a statement of the ârelevance of the incomplete or unavailable information to evaluating reasonably foreseeable significant adverse impacts on the human environmentâ; (3) a âsummary of existing credible scientific evidence ... relevant to evaluating the reasonably foreseeable adverse impactsâ; and (4) the agencyâs âevaluation of such impacts based upon theoretical approaches or research methods generally accepted in the scientific community.â Id. § 1502.22(b). Section 1502.22(b) clarifies that reasonably foreseeable effects âinclude!)] impacts which have catastrophic consequences, even if their probability of occurrence is low.â
Much of the information missing from the EIS concerns animal populations potentially affected by oil exploration and production under the leases. The missing information concerns such things as population levels of various species of animals in the Chukchi Sea, including endangered or threatened animals; the locations of various animal populations during the year; the feeding and breeding habits of various animal populations; and the vulnerability of various animal populations to drilling and other exploration- and production-related activities.
With respect to the potential environmental harm from a large oil spill, BOEM concluded that the missing information was not essential to a reasoned choice among the alternatives. It wrote in the SEIS, â[I]n the unlikely event of a large oil spill, it is well-understood that environmental impacts could be severe. The severity of potential impacts would be nearly identical under any action alternative; therefore, very specific types of information relevant to species, particular life history traits, or behavior do not help substantially in distinguishing among alternatives.â With respect to other activities or events with potential adverse impacts on the animal populations in the Chukchi Sea, BOEM concluded that sufficient protections would be provided by the requirements of other environmental statutes, such as the Clean Air Act, the Marine Mammal Protection Act (âMMPAâ), and the ESA, and by the requirement under NEPA to provide site-specific analyses at later stages of development.
Based on these conclusions, BOEM stated in the SEIS that it did not consider any of the incomplete or unavailable information at issue to be âessential to a reasoned choice among alternativesâ at this stage of the development process. 40 C.F.R. § 1502.22(a). BOEM therefore did not determine whether the information was unobtainable âbecause the overall costs of obtaining it are exorbitant or the means to
In Village of False Pass v. Clark, 733 F.2d 605 (9th Cir.1984), we reviewed an EIS of an oil and gas lease sale under OCSLA. The plaintiff had argued that the commitment made by the government when entering into leases under OCSLA is so substantial that a fully exhaustive environmental analysis under NEPA had to be performed at the lease sale stage. We disagreed, writing:
NEPA may require an environmental impact statement at each stage: leasing, exploration, and production and development. Furthermore, each stage remains separate. The completion of one stage does not entitle a lessee to begin the next.
Id. at 614. We wrote to the same effect in Northern Alaska Environmental Center:
[Projects [for the development of oil and gas natural resources] generally entail separate stages of leasing, exploration and development. At the earliest stage, the leasing stage we have before us, there is no way of knowing what plans for development, if any, may eventually materialize.
A lease sale under OCSLA is analogous to a âprogrammaticâ plan. The required level of analysis in an EIS is different for programmatic and site-specific plans. We wrote in Friends of Yosemite Valley v. Norton, 348 F.3d 789 (9th Cir.2003):
An agencyâs planning and management decisions may occur at two distinct administrative levels:
(1) the âprogrammatic levelâ at which the [agency] develops alternative management scenarios responsive to public concerns, analyzes the costs, benefits and consequences of each alternative in an [EIS], and adopts an amendable [management] plan to guide management of multiple use resources; and (2) the implementation stage during which individual site specific projects, consistent with the [management] plan, are proposed and assessed.
Ecology Ctr., Inc. v. United States Forest Serv., 192 F.3d 922, 923, [n. 2] (9th Cir.1999). An EIS for a programmatic plan ... must provide âsufficient detail to foster informed decision-making,â but âsite-specific impacts need not be fully evaluated until a critical decision has been made to act on site development.â N. Alaska Envtl. Ctr. v. Lujan, 961 F.2d 886, 890-91 (9th Cir.1992).
Id. at 800 (alterations in original).
Regardless of whether a programmatic or site-specific plan is at issue, NEPA requires that an EIS analyze environmental consequences of a proposed plan as soon as it is âreasonably possibleâ to do so. We wrote in Kern v. US. Bureau of Land Management, 284 F.3d 1062 (9th
Once an agency has an obligation to prepare an EIS, the scope of its analysis of environmental consequences in that EIS must be appropriate to the action in question. NEPA is not designed to postpone analysis of an environmental consequence to the last possible moment. Rather, it is designed to require such analysis as soon as it can reasonably be done. If it is reasonably possible to analyze the environmental consequences in an EIS for [a Resource Management Plan], the agency is required to perform that analysis.
Id. at 1072 (citation omitted); see also Pac. Rivers Council v. U.S. Forest Serv., 689 F.3d 1012, 1025-27, 1029-30 (9th Cir.2012), dismissed as moot,âU.S.-, 133 S.Ct. 2843, 186 L.Ed.2d 881 (2013). This is not to say that an agency must provide the most extensive environmental analysis possible at the earliest possible moment, for an agency has some flexibility in deciding the level of analysis to be performed at a particular stage. We will defer to the agencyâs judgment about the appropriate level of analysis so long as the EIS provides as much environmental analysis as is reasonably possible under the circumstances, thereby âprovid[ing] sufficient detail to foster informed decision-makingâ at the stage in question. Friends of Yosemite Valley, 348 F.3d at 800 (internal quotation marks omitted).
In the case before us, we conclude that BOEM has reasonably concluded that the missing information from the FEIS and SEIS is not âessentialâ to informed deci-sionmaking at the lease sale stage. We agree with BOEM that compliance with statutes such as the MMPA and the ESA will provide protection for animals covered by those statutes. The MMPA generally prohibits the âtakeâ of marine mammals. 16 U.S.C. § 1371(a). A âtakeâ encompasses any act of âtormentâ or âannoyanceâ that âhas the potential to injure ... or ... disturb a marine mammal or marine mammal stock in the wild by causing disruption of natural behavioral patterns, including, but not limited to, migration, surfacing, nursing, breeding, feeding, or sheltering.â id § 1362(13), (18)(A)(i)-(ii). Unlawful âtakesâ trigger civil and criminal penalties. Id. § 1375(a)(1), (b). Further, under the ESA § 7(a)(2), 16 U.S.C. § 1536(a)(2), BOEM must consult with the National Marine Fisheries Service and the U.S. Fish and Wildlife Service to âinsure that any action authorized, funded, or carried out by such agency ... is not likely to jeopardize the continued existence of any endangered species or threatened species.â If an action is likely to jeopardize a species, the acting agency must determine whether any âreasonable and prudent alternativesâ exist that will avoid jeopardizing that species. 16 U.S.C. § 1536(b)(3)(A). We recognize that BOEM has already consulted with these agencies at the lease sale stage. It may well have to consult with them again at the development and production stage when specific plans have been proposed and site-specific activities are contemplated. (We note that it may also have to consult again at the lease sale stage, once it has performed a proper analysis of the estimated overall oil production.) Because these statutes provide additional protections for animals in the Chukchi Sea, they support BOEMâs conclusion that missing information about these animals was not âessentialâ at this stage.
We also agree with BOEM that further environmental analysis will be appropriate at a later stage. In BOEMâs words, âcertain items of presently missing or incomplete information will be known (and utilized to avoid or minimize adverse impacts) at a later stage of OCS Lands Act environ
Of course, we recognize that our discussion and decision in the next Section regarding B OEMâs one billion barrel estimate may have some effects upon the remainder of the FEIS. But we will not at this time speculate about the extent of those effects, if any. Defendants are in the best position to analyze those effects, if any, and have the duty to analyze them in the first instance.
B. One Billion Barrel Estimate
Plaintiffs contend that BOEM chose an arbitrary number for the total barrels of economically recoverable oil from Lease Sale 193. The FEIS estimated the amount of recoverable oil by estimating production from the âfirst offshore oil fieldâ that would be developed within the area of the leases. BOEM did not make any estimate of recoverable oil from additional fields that might be developed. The FEIS specified that the ârecoverable oil resources from this field are assumed to be 1 billion barrels (Bbbl).â The FEIS then used the one billion barrel estimate as the basis for its environmental analysis.
We must determine whether BOEM has articulated a rational basis for its decision to use the one billion barrel estimate. Morar-Meraz v. Thomas, 601 F.3d 933, 939 (9th Cir.2010). We must reverse a decision as arbitrary and capricious if
the agency relied on factors Congress did not intend it to consider, entirely failed to consider an important aspect of the problem, or offered an explanation that runs counter to the evidence before the agency or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise.
Lands Council II, 537 F.3d at 987 (internal quotation marks omitted). For the reasons that follow, we conclude that BOEMâs one billion barrel estimate is arbitrary and capricious.
1. The Selection of One Billion Barrels
BOEM first announced it was developing an EIS in preparation for Lease Sale 193 in July 2005. According to internal BOEM emails, BOEM analyst Jim Craig was assigned to provide âresource estimates and a scenarioâ which other BOEM scientists would use to analyze environmental effects. Craig emailed his supervisor, Deborah Cranswick, stating that he believed that â[t]he reasonably foreseeable scenarioâ should include âoil production from the first field only, not the full economic potential.â Craigâs reason for focusing on the first field production was practical; he would have to wait for about two months to have information that would allow him to develop a scenario for the entire area covered by the lease sale. Craig stated in his email, âYou realize that we wonât have the 2005 resource assessment numbers until Sept, so we must base the scenario on the âfirst developmentâ not the total economic potential.â Craig also indicated that this emphasis on the first oil field was a âdeparture from previous work.â
Craig asked Cranswick whether the scenario should employ a single estimate of oil production from that first field, or whether
There is a gap in the email chain in our record, so we do not know Cranswickâs next response to Craig. But we do know that in a subsequent email from Craig to Cranswick on August 2, Craig proposed a single one billion barrel estimate as an alternative to using a range that was âtoo broadâ:
Attached is a table with E & D data. If this represents too broad of a range, then I think we should fall back to a single volume (1.0 Bbbl) for the EIS analysis with a corresponding set of single E & D numbers. Itâs hard to have it both ways (very narrow range) when these figures are entirely speculative. There are two clear options:
1) 500-1500 MMbbl, as a uniform distribution (every point in range is equally likely). This will require a low and high case analysis.
2) 1.0 Bbbl as a single point estimate with no confidence interval. This will require a mostly likely case analysis only.
Although it would be nice to propose a recoverable oil volume of 932 MMbbl +/- 134 MMbbl in a 90% confidence interval, we donât have any data to support it.
Pick (1) or (2), but not (1) and (2).
On August 3, Cranswick emailed Craig a data chart reflecting Craigâs second option. It contained only a single one billion barrel estimate.
On that same day, Craig emailed to Cranswick a draft scenario relying on the one billion barrel estimate of oil production. This draft explained:
The scenario assumed for environmental analysis involves the discovery, development, and production of the first oil field in the Chukchi sale area. Ultimately recoverable oil resources from this field are assumed to be 1 billion barrels (Bbbl). Smaller oil volumes are not likely to be economic to produce and single pools containing larger volumes are increasingly rare. If oil prices drop below $30.00 per barrel (they are above $50.00 when this scenario was written), exploration in the Chukchi OCS is expected to be minimal and oil discoveries may not be developed.
The draft also pointed out that âthe mean recoverable oil resource [in the Chukchi Sea] is 12 Bbbl with a 5% probability of 29 Bbbl.â Craig also prepared a chart for Cranswick comparing the numbers Craig had selected for the Lease Sale 193 EIS to an EIS prepared for the Chukchi Sea and Hope Sea Basin for the 2002-2007 Five Year Oil and Gas Leasing Program. That previous EIS had estimated a range for economical oil production from 0.96 billion barrels to 2.42 billion barrels.
On August 10, Cranswick circulated the Lease Sale 193 EIS scenario to other BOEM scientists who would be working on the EIS. The scenario contained the one billion barrel estimate. Cranswick explained in an email that
[t]he scenario is based on a one mid-range economic resource number (note â this is not necessarily the most likely. A lower volume is more likely to*501 occur but less likely to be developed from an economic standpoint; a higher volume is less likely to occur but more likely to be developed).
Several BOEM employees expressed concern with the agencyâs proposed scenario. For example, one NEPA analyst employed by BOEM, Dee Williams, wrote, âI donât understand why [the agency] doesnât use their sophisticated assessment indices to impose a more definitive likely scenario. Clearly, it is impossible to predict âwith certaintyâ, but the narrative needs to inspire greater public confidence by explaining the parameters of reasonable expectations.â Williams further stated:
If it becomes economical to build one platform to produce an estimated 1 billion barrels, and there is between 12 and 29 billion barrels that are recoverable, why is the scenario not compelled to imagine more than one platform (i.e. is a single platform always the initial scenario, in which case maybe we should just explain that)?
Cranswick responded that âthe initial scenario is one platform because we canât have only a partial platform if that is all that the resource estimate supports].â At the same time, Cranswick suggested that smaller oil developments would be associated with the first oil platform. âOnce the first platform goes in, it is likely that additional satellite subsea completions would be developed before another host platform would be considered.â
Once the draft EIS was completed, BOEM sought comments from other agencies and from the public. Numerous outside commentators expressed concern about the scenario BOEM had developed. For example, the Environmental Protection Agency wrote that
the hypothetical development scenario that is used in the document add[s] additional layers of uncertainty regarding the probabilities of exploration, production and development activities and the risks associated with those activities.... EPA is concerned that, overall, the depth and diversity of uncertainties presented in the document resulted in the lack of adequate support for many of the documentâs conclusions.
The Division of Migratory Bird Management at the U.S. Fish and Wildlife Service (âFWSâ) similarly challenged the one billion barrel estimate as inaccurate:
The basic assumptions used in the analysis of effects are flawed with regards to the size of development scenarios. The [Draft EIS (âDEISâ)] states that the current petroleum assessment indicates a mean recoverable oil resource of 12 billion barrels; yet all environmental analyses reported in the DEIS are based on a development of 1 billion barrels, thereby significantly underestimating likely scenarios.
The Division recommended that BOEM not proceed with the lease sale until problems with the EIS were corrected. Public commentators similarly pointed to flaws in employing a one billion barrel production estimate, including that such an estimate was âbased on a price of oil at half the current market value,â that the estimate âseverely understates the true cumulative impactsâ of oil production, and that it was ânowhere ... justified with scientific analysis.â Despite these criticisms, BOEM continued to rely on its one billion barrel estimate. The one billion barrel estimate was the basis for the entire FEIS, including its analysis of the risk of a large oil spill. For example, BOEM instructed the FWS to rely on that estimate in that agencyâs analysis of whether the lease sale would jeopardize listed threatened species such as the spectacled and Stellerâs eiders. Had FWS made a jeopardy finding,
2. Arbitrary and Capricious
Plaintiffs contend that the one billion barrel estimate was chosen arbitrarily, and that BOEM did not provide an adequate explanation for its selection. We agree for three reasons.
First, BOEM has not justified its choice of the lowest possible amount of oil that was economical to produce as the basis for its analysis. The draft EIS scenario stated that the agency chose to focus on a one billion barrel estimate in part because any volume lower than one billion barrels would not be economical to produce. At the same time, BOEM was well aware that if any oil was produced from Lease Sale 193, the economically recoverable oil was very likely to exceed one billion barrels. In an August 18, 2005, email commenting on the in-progress draft EIS, Jim Craig wrote, âWe assume 1 billion bbl for the first field, but there is another 11 Bbbl that is economic at $70.â Craig attached a table to a December 2005 email, listing âEstimates for Speculative Oil and Gas Reserves,â specifying a range between 1.0 and 6.1 billion barrels for the âChukchi Shelf.â Finally, in a May 2006 email Craig wrote, âThe â1-billion barrel, first fieldâ assumption is subjective (âfor purposes of analysisâ) and represents only a fraction of the full economic resource potential in the Chukchi (which was recently published).â
The mean estimate of economical oil production, at the center of the distribution curve, is by definition a more likely occurrence than is the lowest estimate of viable oil production. Previous ElSes in the Chukchi Sea had used the mean estimate of oil production as the basis for their analyses, and those ElSes had also included low and high estimates. For example, BOEM previously leased portions of the Chukchi Sea in now-expired Lease Sale 109. The parcels leased in Lease Sale 109 overlap substantially with the parcels leased in Lease Sale 193. Documents prepared in advance of Lease Sale 109 stated that â[t]he mean resource estimate ... is 2.68 billion barrels of oil with a 20 percent chance of a discovery of commercially recoverable oil.â In estimating the effects of oil spills from Lease Sale 109, BOEM âassume[d] the full development of the resource estimate of 2.68 billion barrels.â In contrast, while estimates in the record about the economically recoverable amount of oil from Lease Sale 193 vary, nowhere is the mean amount of economical production calculated to be less than 2.37 billion barrels. But the FEIS for Lease Sale 193 uses one billion rather than 2.37 billion barrels as the basis for its analysis of environmental consequences.
BOEMâs primary explanation for using its low-end estimate for oil production is that this scenario overestimates the likely amount of production. BOEM emphasizes that because of the remoteness of the area and the risk of economic failure, any oil production activity is an unlikely result of the lease sale. More specifically, BOEM estimates that there is a less than 10 percent likelihood that oil development in the region will occur. Defendants argue that since the most likely foreseeable outcome is no oil development at all, one billion barrels of oil production is actually a generous estimate.
This analysis is flawed. The assumption that there is a 10 percent chance of commercial oil development is itself without a rational basis in the record. Jim Craig first developed the estimate âoff the top of [his] headâ in an email exchange. That calculation contradicts estimates
Second, the FEIS did not take into account variation in oil prices in arriving at the estimate that one billion barrels of oil are economically recoverable. An assumption of stable prices ignores the fact that the amount of economically recoverable oil varies substantially depending on oil prices. This may be seen, for example, in a 2006 report of the