Sierra Club v. Federal Energy Regulatory Commission

U.S. Court of Appeals8/22/2017
View on CourtListener

AI Case Brief

Generate an AI-powered case brief with:

📋Key Facts
⚖Legal Issues
📚Court Holding
💡Reasoning
🎯Significance

Estimated cost: $0.001 - $0.003 per brief

Full Opinion

Opinion concurring in part and dissenting in part filed by Circuit Judge BROWN. ■

GRIFFITH, Circuit Judge:

Environmental groups and landowners have challenged the decision of the Federal Energy Regulatory Commission to approve the construction and operation of three new interstate natural-gas pipelines in the southeastern United States. Their primary argument is that the agency’s assessment of the environmental impact of the pipelines was inadequate. We agree that FERC’s environmental impact statement did not contain enough information on the greenhouse-gas emissions that will result from burning the gas that the pipelines will carry. In all other respects, we conclude that FERC acted properly. We thus grant Sierra Club’s petition ‘for review and remand for preparation of a conforming environmental impact statement.

I

The Southeast Market Pipelines Project comprises three natural-gas pipelines now under construction in Alabama, Georgia, and Florida. The linchpin of the project is the Sabal Trail pipeline, which will wend its way from Tallapoosa County in eastern Alabama, across southwestern Georgia, and down to Osceola County, Florida, just south of Orlando:' a journey of nearly five hundred miles. Sabal Trail will connect the other two portions of the project. The first—the: Hillabee Expansion—will boost the capacity of an existing pipeline in Alabama, which will feed gas to Sabal Trail’s upstream end for transport to Florida. At the downstream end of Sabal Trail will be the Florida Southeast Connection, which will link to a powĂ©r plant in Martin County, Florida, 120 miles away. Shorter spurs will join Sabal Trail to other proposed and existing power plants and pipeline networks. By its scheduled completion in 2021, the project will be able to carry over one billion cubic feet of natural gas per day.

The three segments of the project have different owners,1 but they share a oom-*1364mon purpose: to serve Florida’s growing demand for natural gas and the electric power that natural gas can generate. At present, only two major natural-gas pipelines serve the state, and both are almost at capacity. Two major utilities, Florida Power & Light and Duke Energy Florida, have already committed to buying nearly all the gas the project will be able to transport. Florida Power & Light claims that without this new project, its gas needs will begin to exceed its supply this year. But the project’s developers also indicate that the increased transport of natural gas will make it possible for utilities to retire older, dirtier coal-fired power plants.

Despite these optimistic predictions, the project has drawn opposition from several quarters. Environmental groups fear that increased burning of natural gas will hasten climate change and its potentially catastrophic consequences. Landowners in the pipelines’ path object to the seizure of their property by eminent domain. And communities on the project’s route are concerned that pipeline facilities will be built in low-income and predominantly minority areas already overburdened by industrial polluters.

Section 7 of the Natural Gas Act places these disputes into the bailiwick of the Federal Energy Regulatory Commission (FERC), which has jurisdiction to approve or. deny the construction of interstate natural-gas pipelines. See 15 U.S.C. § 717f. Before any such pipeline can be built, FERC must grant the developer a “certificate of public convenience and necessity,” id. § 717f(c)(l)(A), also called a Section 7 certificate, upon a finding that the project will serve the public interest, see id. § 717f(e). FERC is also empowered to attach “reasonable terms and conditions” to the certificate, as necessary to protect the public. Id. A certificate holder has the ability to acquire necessary rights-of-way from unwilling landowners by eminent domain proceedings. See id. § 717f(h).

FERC launched an environmental review of the proposed project in the fall of 2013. The agency understood that it would need to prepare an environmental impact statement (EIS) before approving the project, as the National Environmental Policy Act of 1969 (NEPA) requires for each “major Federal action[] significantly affecting the quality of the human environment.” See 42 U.S.C. § 4332(2)(C). FERC solicited public comment and held thirteen public meetings on the project’s environmental effects, and made limited modifications to the project plan in response to public concerns, before releasing a draft impact statement in September 2015 and a final impact statement in December 2015. In the meantime, the pipeline developers formally applied for their Section 7 certificates in September and November 2014.

In the Certificate Order, issued on February 2, 2016, FERC granted the requested Section 7 certificates and approved construction of all three project segments, subject to compliance with various conditions not at issue here. Order Issuing Certificates and Approving Abandonment, Fla. Se. Connection, LLC, 154 FERC ¶ 61,080 (2016) (Certificate Order). This order recognized a number of parties as intervenors in the agency proceedings, among them three environmental groups (Sierra Club, Flint Riverkeeper, and Chattahoochee Riv-erkeeper) and two Georgia landowners whose land Sabal Trail will cross (GBA Associates and K. Gregory Isaacs). These parties timely sought rehearing and a stay of construction; FERC agreed to entertain their arguments but denied a stay. Construction on the pipelines began in August 2016. On September 7, 2016, FERC *1365issued its Rehearing Order, denying rehearing and declining to rescind the pipelines’ certificates. Order on Rehearing, Fla. Se. Connection, LLC, 156 FERC ¶ 61,160 (2016) (Rehearing Order).

Both the environmental groups (collectively, “Sierra Club”) and the landowners timely petitioned our court for review of the Certificate Order and the Rehearing Order. Sierra Club argues that FERC’s environmental impact statement failed to adequately consider the project’s contribution to greenhouse-gas emissions and its impact on low-income and minority communities. Sierra Club also contends that Sabal Trail’s service rates were based on an invalid methodology. The landowners allege further oversights in the EIS, dispute the public need for the project, and assert that FERC used an insufficiently transparent process to approve the pipeline certificates. Their petitions were consolidated before us.

II

We have jurisdiction to hear these petitions under the Natural Gas Act. See 15 U.S.C. § 717r(b). Any party to a proceeding under the Act who is “aggrieved” by a FERC order may petition for review of that order in our court, provided that they first seek rehearing before FERC. Id. § 717r(a)-(b). Sierra Club was an interve-nor in the proceedings on all three pipeline applications, see Certificate Order App. A, and the landowner petitioners were inter-venors in the Sabal Trail proceedings, see id.

A party is “aggrieved” by a FERC order if it challenges the order under NEPA and asserts an environmental harm. See Gunpowder Riverkeeper v. FERC, 807 F.3d 267, 273-74 (D.C. Cir. 2015). A landowner forced to choose between selling to a FERC-certified developer and undergoing eminent domain proceedings is also “aggrieved” within the meaning of the Act. See B & J Oil & Gas v. FERC, 353 F.3d 71, 75 (D.C. Cir. 2004); Moreau v. FERC, 982 F.2d 556, 564 n.3 (D.C. Cir. 1993). Sierra Club falls into the former camp, and the Georgia landowners into the latter.

We also have an independent duty to ensure that at least, one petitioner has standing under Article III of the Constitution. See Ams. for Safe Access v. DEA, 706 F.3d 438, 442-43 (D.C. Cir. 2013). A petitioner invoking federal-court jurisdiction has the burden to establish that she has suffered an injury in fact that is fairly traceable to the challenged action of the defendant and “likely” to be redressed by a favorable judicial decision. WildEarth Guardians v. Jewell, 738 F.3d 298, 305 (D.C. Cir. 2013). And an association, like Sierra Club, can sue on behalf of its members if at least one member would have standing to sue in her own right, the organization is suing to vindicate interests “germane to its purpose,” and nothing about the claim asserted or the relief requested requires an individual member to be a party. Sierra Club v. FERC, 827 F.3d 36, 43 (D.C. Cir. 2016). On direct review of agency action, an association can establish its standing by having its individual members submit affidavits to accompany the association’s opening brief. See Pub. Citizen, Inc. v. Nat’l Highway Traffic Safety Admin., 489 F.3d 1279, 1289 (D.C. Cir. 2007).

Several individual Sierra Club members submitted such affidavits, explaining how the pipeline project would harm their “concrete aesthetic and recreational interests.” WildEarth, 738 F.3d at 305. For example, one member, Robin Koon, explained that the Sabal Trail pipeline will cross his property (on an easement taken by eminent domain), that con*1366struction noise will impair his enjoyment of his daily activities, and that trees shading his house will be permanently removed. Other Sierra Club members similarly averred that the pipeline project will affect their homes and daily lives. “Such credible claims of exposure to increased noise and its disruption of daily activities, backed up by specific factual representations in an affidavit -or-declaration, are sufficient to satisfy Article Ill’s injury-in-fact requirement.” Sierra Club, 827 F.3d at 44. And nobody disputes that the prevention of this sort of injury is germane to Sierra Club’s conservation-oriented purposes, ■ or. cites any reason why these individual members would need to join the petition in their own names.

Because they allege concrete injury from FERC’s order certifying the pipeline project, and because that certification was based on an allegedly inadequate environmental impact statement, these Sierra. Club members, and therefore Sierra Club itself, have standing to object to any deficiency in the environmental impact statement.2 See WildEarth Guardians, 738 F.3d at 306-08. The deficiency need' not be directly tied to the members’ specific injuries. For example, Sierra Club may argue that FERC did not adequately consider the pipelines’ contribution to climate change. See id. The members’ injuries are caused by the allegedly unlawful Certificate Order, and would be redressed by vacatur of that order on the basis of any defect in the environmental impact statement. See id. at 308.3

Transco, owner of the Hillabee Expansion, argues that no Sierra Club member has alleged an injury caused by Tran-sco’s section of the overall project, which would suggest ■ that Sierra Club lacks standing to seek the vacatur of Hillabee’s certificate. Transco thus implicitly argues that the Certificate Order is- severable. Under this view, if Sierra Club succeeds on the merits, but has standing to challenge only Sabal Trail’s certificate, we could vacate only the portion of the Certificate Order pertaining to Sabal Trail, and leave the rest intact.

The question whether an agency order is severable turns on the agency’s intent. See Epsilon Elecs., Inc. v. U.S. Dep’t of Treasury, 857 F.3d 913, 929 (D.C. Cir. 2017). “Where 'there is substantial doubt that the agency would have adopted the same disposition regarding the unchallenged portion if the challenged portion were subtracted, partial affirmance is improper,” Id. (quoting North Carolina v. FERC, 730 F.2d 790, 795-96 (D.C. Cir. 1984)). Since the beginning of its environmental review, FERC has treated the project as a single, integrated proposal. See Notice of Intent to Prepare an Environmental Impact Statement for the Planned Southeast Market Pipelines Project, 79 Fed. Reg. 10,793, 10,794 (Feb. 26, 2014) *1367(explaining that PERC would prepare a single EIS for the three pipelines, to help the agency determine “whether' the SMP Project is in the public convenience and necessity”). That characterization carried through to the Certificate Order. See J.A. 1075 (describing the pipelines as “separate but connected” and noting that the Hilla-bee Expansion’s purpose is to give Sabal Trail’s customers access to upstream gas supplies); J.A. 1096 (explaining that in the absence of Sabal Trail, existing pipelines will not be able to deliver the gas that the Florida Southeast Connection requires).

We substantially doubt that FERC would have approved the Southeast Market Pipelines Project only in part, and we especially doubt that. the agency would have certified either of the other two segments if Sabal Trail were not part of the project. Because Sierra Club and the landowners have alleged injury-in-fact caused by Sabal Trail, and because the Certificate Order is not severable, both sets of petitioners have standing to challenge the Certificate Order as a whole.

Having concluded that we have jurisdiction to entertain all of petitioners’ claims, we turn to the merits of those claims.

Ill .

Both sets of petitioners rely heavily on the National Environmental . Policy Act of 1969, Pub. L. No. 91-190, 83 Stat. 852 (1970). NEPA “declares a broad national commitment to protecting and promoting environmental quality,” and brings that commitment to bear on the operations of the federal government. Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 348, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989). The statute “commands agencies to imbue their decisionmaking, through, the use of certain procedures, with our country’s commitment to environmental salubrity.” Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190, 193-94 (D.C. Cir. 1991). One of the most important procedures NEPA mandates is the preparation, as part of every “major Federal aetion[] significantly affecting the quality of the human environment,” of a “detailed statement” discussing and disclosing the environmental impact of the action. 42 U.S.C. § 4332(2)(C).

This environmental impact statement, as it has come to be called, has two purposes. It forces the agency to take a “hard look” at the environmental consequences of its actions, including alternatives to its proposed course. See id. § 4332(2) (C) (iii); Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 462 U.S. 87, 97, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983). It also ensures that these environmental consequences, and the agency’s consideration of them, are disclosed to the public. See WildEarth Guardians, 738 F.3d at 302. Importantly, though, NEPA “directs agencies only to look hard at the environmental effects of their decisions, and not to take one type of action or another.” Citizens Against Burlington, 938 F.2d at 194, That is, the statute is primarily information-forcing.

The role of the courts in reviewing agency compliance with NEPA is accordingly limited. Furthermore, because NEPA does not create a private right of action, we can entertain NEPA-based challenges only under the Administrative Procedure Act and its deferential standard of review. See Theodore Roosevelt Conservation P’ship v. Salazar, 616 F.3d 497, 507 (D.C. Cir. 2010), That is, our mandate “is ‘simply to ensure that the agency has adequately considered and disclosed the environmental impact of its actions and that, its decision is not arbitrary or capricious.’” WildEarth Guardians, 738 F.3d at 308 (quoting City of Olmsted Falls v. FAA, 292 *1368F.3d 261, 269 (D.C. Cir. 2002)). We should not “ ‘flyspeck’ an agency’s environmental analysis, looking for any deficiency no matter how minor.” Nevada v. Dep’t of Energy, 457 F.3d 78, 93 (D.C. Cir. 2006) (citation omitted).

But at the same time, we are responsible for holding agencies to the standard the statute establishes. An EIS is deficient, and the agency action it un-dergirds is arbitrary and capricious, if the EIS does not contain “sufficient discussion of the relevant issues and opposing viewpoints,” Nevada, 457 F.3d at 93 (quoting Nat. Res. Def. Council v. Hodel, 865 F.2d 288, 294 (D.C. Cir. 1988)), or if it does not demonstrate “reasoned decision-making,” Del. Riverkeeper Network v. FERC, 753 F.3d 1304, 1313 (D.C. Cir. 2014) (quoting Found. on Econ. Trends v. Heckler, 756 F.2d 143, 154 (D.C. Cir. 1985)). The overarching question is whether an EIS’s deficiencies are significant enough to undermine informed public comment and informed decisionmaking. See Nevada, 457 F.3d at 93. This is NEPA’s “rule of reason.” See Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752, 767, 124 S.Ct. 2204, 159 L.Ed.2d 60 (2004).

With those principles in mind, we direct our attention to the specific deficiencies the petitioners have alleged in the EIS for the Southeast Market Pipelines Project. As noted above, FERC prepared a single unified EIS for the project’s three pipelines, and no party has challenged that approach. Thus, for purposes of our NEPA analysis, we will consider the project as a whole.

A

The principle of environmental justice encourages agencies to consider whether the projects they sanction will have a “disproportionately high and adverse” impact on low-income and predominantly minority communities.4 See J.A. 1353-54. Executive Order 12,898 required federal agencies to include environmental-justice analysis in their NEPA reviews, and the Council on Environmental Quality, the independent agency that implements NEPA, see 42 U.S.C. § 4344, has promulgated environmental-justice guidance for agencies, see J.A. 1369-78.

Sierra Club argues that the EIS failed to adequately take this principle into account. Like the other components of an EIS, an environmental justice analysis is measured against the arbitrary-and-capricious standard. See Cmtys. Against Runway Expansion, Inc. v. FAA, 355 F.3d 678, 689 (D.C. Cir. 2004).5 The analysis must be “reasonable and adequately explained,” but the agency’s “choice among reasonable analytical methodologies is entitled to deference.” Id. As always with NEPA, an agency is not required to select the course of action that best serves environmental justice, only to take a “hard look” at environmental justice issues. See Latin Ams. for Social & Econ. Dev. v. Fed. Highway Admin., 756 F.3d 447, 475-77 (6th Cir. 2014). We conclude that FERC’s discussion of environmental justice in the EIS satisfies this standard.

The EIS explained that 83.7% of the pipelines’ proposed route would cross *1369through, or within one mile of, environmental-justice communities (defined as census tracts where the population is disproportionately below the poverty line and/or disproportionately belongs to racial or ethnic minority groups). That percentage varied from 54 to 80 percent for the alternative routes proposed by stakeholders and commenters, albeit with only one option below 70 percent. This type of data appeared not only in the section of the EIS specifically dedicated to environmental justice, but also in the chapter that compared the various alternative routes. That later chapter weighed environmental-justice statistics alongside factors like total route length, wetlands impact, and the number of homes near the route. It also discussed one additional proposed route, which would cross the Gulf of Mexico and avoid Georgia completely. This option would affect far fewer environmental-justice communities, but in FERC’s assessment would be infeasible because it would cost an additional two billion dollars.

FERC concluded that the various feasible alternatives “would affect a relatively similar percentage of environmental justice populations,” and that the preferred route thus would not have a disproportionate impact on those populations. See J.A. 836. The agency also independently concluded that the project would not have a “high and adverse” impact on any population,- meaning, in the agency’s view, that it could not have a “disproportionately high and adverse” impact on any population, marginalized or otherwise.6

Sierra Club contends that FERC misread “disproportionately high and adverse,” the standard for when a particular environmental effect raises an environmental-justice concern. By Sierra Club’s lights, any effect can -fulfill the test, regardless of its intensity, extent, or duration, if it is not beneficial and falls disproportionately on environmental-justice communities. But even if we assume that understanding to be correct, we cannot see how this EIS was deficient. It discussed the intensity, extent, and duration of the pipelines’ environmental effects, and also separately discussed the fact that those effects will disproportionately fall on environmental-justice communities. Recall that the EIS informed readers and the agency’s ultimate decisionmakers that 83.7% of the pipelines’ length would be in or near environmental-justice communities. The EIS also evaluated route alternatives in part by looking at the number of environmental-justice communities each would cross,' and the mileage of pipeline each would place in low-income and minority areas. FERC thus grappled with the disparate impacts of the various possible pipeline routes. Perhaps Sierra Club would have a stronger claim if the agency had refused entirely to discuss the demographics of the populations thát will feel the pipelines’ effects, and had justified this refusal by pointing to the limited intensity, extent, and duration of those effects. However, as the EIS stands, we see no deficiencies serious enough to defeat the statute’s goals of fostering well-informed decisionmaking and public comment. See Nevada, 457 F.3d at 93.

The same goes for Sierra Club’s other arguments. The agency’s methodology was reasonable, even where it deviated from what Sierra Club would have preferred. See Runway Expansion, 355 F.3d at 689. Take the agency’s decision to compare the demographics along the various proposed routes to each other instead of “the gener*1370al population.” Sierra Club Opening Br; 18. An EIS is meant to help agency heads choose among the relevant alternatives, including the alternative of taking no action, and to help the public weigh in. Thus, FERC’s decision to directly compare the proposed alternatives to one another, rather than to some broader population, was reasonable under the circumstances. See id. (approving an environmental-justice review that compared “the population predicted to be affected by ... [a] project to the demographics of the population that otherwise might conceivably be affected” by the project). Another methodology might be more appropriate in a case where some feasible alternative, with a lower environmental-justice impact,..has been left out of the analysis. However, no party has offered any such alternative here.

Sierra Club is particularly concerned about Sabal Trail’s plan to build a compressor .station (a facility that helps “pump” gas along the pipeline, and gives off ah- and noise pollution while doing so) in an African American neighborhood of Albany, Dougherty County, Georgia. The agency identified environmental-justice communities by looking at the demographics of census tracts, which are county subdivisions created to organize census data. The neighborhood in question is a 100% African American census block, an even smaller census subdivision, but because it sits in the midst .of a majority-white census tract, FERC did not designate it an environmental-justice community. Sierra Club’s objection to this omission elevates form over substance. The goal of an environmental-justice analysis is satisfied if an agency recognizes and discusses a project’s impacts on predominantly-minority communities, even if it does not formally label each such community an “environmental justice community.” FERC did recognize the existence and demographics of the neighborhood in question, and discussed the neighborhood extensively. The EIS listed community features, including subdivisions, schools, and churches, along with their distances from the proposed compressor station, and explained that the station’s noise and air-quality effects on these locations were expected to remain within acceptable limits.

More persuasive is Sierra Club’s argument that FERC disregarded the extent to which Dougherty County is already overburdened with pollution sources. A letter to FERC from four members of Georgia’s congressional delegation cites the grim statistics: southern Dougherty County has 259 hazardous-waste facilities, 78 air-polluting facilities, 20 toxic-polluting facilities, and- 16 water-polluting facilities. The EIS did not mention these existing polluters in its discussion of Dougherty County. Sierra Club thus argues that FERC inadequately considered the project’s “cumulative impacts,” that is, its effects taken in combination with existing environmental hazards in the same area. See 40 C.F.R. § 1508.7; Del Riverkeeper, 753 F.3d at 1319-20.

Perhaps FERC could have said, more, but the discussion it undertook of the cumulative impacts of the proposed route fulfilled NEPA’s goal of guiding informed decisionmaking. The EIS acknowledged that the Sabal Trail project will generate ah* pollution and noise pollution in Albany, and it projected cumulative levels of both of these types of pollution from all sources in the vicinity of the compressor station, finding that both would remain below harmful thresholds.7 We are sensitive to *1371Sierra Club’s broader contention that it is unjust to locate a polluting facility in a community.that already has a high concentration of polluting facilities, even if those older facilities produce pollution of a different type or in different locations. We note, however, that FERC took seriously commenters’ concerns about locating Sabal Trail facilities in Dougherty County. The agency reopened the comment period on the EIS to seek input on relocating the compressor station, and then actually'secured Sabal Trail’s agreement to relocate the station, moving it in part to mitigate effects on environmental-justice communities. The EIS also considered four route alternatives proposed by Sierra Club and its fellow environmental petitioners that would have partially or completely avoided Albany, but rejected them all, mainly on the ground that they would have had a greater overall impact on residences and populated areas.

To sum up, the EIS acknowledged and considered the substance of all the concerns Sierra Club now raises: the fact that the Southeast Market Pipelines Project will travel primarily through low-income and minority communities, and the impact of the pipeline on the city of Albany and Dougherty County in particular. The EIS also laid out a variety of alternative approaches with potential to address those concerns, including those proposed by, petitioners, and explained why, in FERC’s view, they would do more harm than good. The EIS also gave the public and agency decisionmakers the qualitative and quantitative tools they needed to make an informed choice for themselves. NEPA requires nothing more.

'S

It’s not just the journey, though, it’s also the destination. All the natural' gas that will travel through these pipelines will be going somewhere: specifically, to power plants in Florida, some of which already exist, others of which are in the planning stages. Those power plants will burn the gas, generating both electricity and carbon dioxide. And once in the atmosphere, that carbon dioxide will add to the greenhouse effect, which the EIS describes as “the primary contributing factor” in global climate change. J.A. 915. The next question before us is whether, and to what extent, the EIS for this pipeline project needed to discuss these “downstream” effects of the pipelines and their cargo. We conclude that at a minimum, FERC should have estimated the amount of power-plant carbon emissions that the pipelines will make possible.

An agency conducting a NEPA review must consider not only the direct effects, but also the indirect environmental effects, of the project under consideration. See 40 C.F.R. § 1502.16(b). “Indirect effects” are those that “are caused by the [project] and are later in time or farther removed in distance, but are still reasonably foreseeable.” Id, § 1508.8(b). The phrase “reasonably foreseeable” is the key here. Effects are reasonably foreseeable if they are “sufficiently likely to occur that a person of ordinary prudence would take [them] into account in reaching a decision,” EarthReports, Inc. v. FERC, 828 F.3d 949, 955 (D.C. Cir. 2016) (citation omitted).

What are the “reasonably foreseeable” effects of authorising a pipeline that will *1372transport natural gas to Florida power plants? First, that gas will be burned in those power plants. This is not just “reasonably foreseeable,” it is the project’s entire purpose, as the pipeline developers themselves explain. See Intervenor Br. 4-5 (explaining that the project “will provide capacity to transport natural gas to the electric generating plants of two Florida utilities”). It is just as foreseeable, and FERC does not dispute, that burning natural gas will release into the atmosphere the sorts of carbon compounds that contribute to climate change.

The pipeline developers deny that FERC would be the legally relevant cause of any power plant carbon emissions, and thus contend that FERC had no obligation to consider those emissions in its NEPA analysis. They rely on Department of Transportation v. Public Citizen, 541 U.S. 752, 124 S.Ct. 2204, 159 L.Ed.2d 60 (2004), a case involving the Federal Motor Carrier Safety Administration’s development of safety standards for Mexican trucks operating in the United States. The agency had proposed those standards because the President planned to lift a moratorium on Mexican motor carriers operating in this country. These standards would require roadside inspections, which had the potential to create adverse environmental effects. The agency’s EIS discussed the effects of these roadside inspections, but Public Citizen contended that the EIS was also required to address the environmental effects of increased truck traffic between the two countries. See id. at 765, 124 S.Ct. 2204.

The Supreme Court sided with the agency. The Court noted that the agency would have no statutory authority to exclude Mexican trucks from the United States once the President lifted the moratorium; it would only have power to set safety rules for those trucks. See id. at 766-67, 124 S.Ct. 2204. And because the agency could not exclude Mexican trucks from the United States, it would have no reason to gather data about the environmental harms of admitting them. The purpose of NEPA is to help agencies and the public make informed decisions. But when the agency has no legal power to prevent a certain environmental effect, there is no decision to inform, and the agency need not analyze the effect in its NEPA review. See id. at 770, 124 S.Ct. 2204.

We recently applied the Public Citizen rule in three challenges to FERC decisions licensing liquefied natural gas (LNG) terminals. See Sierra Club v. FERC (Freeport), 827 F.3d 36 (D.C. Cir. 2016); Sierra Club v. FERC (Sabine Pass), 827 F.3d 59 (D.C. Cir. 2016); EarthReports, Inc. v. FERC, 828 F.3d 949 (D.C. Cir. 2016). Companies can export natural gas from the United States through an LNG terminal, but such natural gas exports require a license from the Department of Energy. See Freeport, 827 F.3d at 40. They also require physical upgrades to a terminal’s facilities. The Department of" Energy has delegated to FERC the authority to license those upgrades. See id. A question presented to us in all of these‘cases was whether FERC, in licensing physical upgrades for an LNG terminal, needed to evaluate the climate-change effects of exporting natural gas. Relying on Public Citizen, we answered no in each case. FERC had no legal authority to consider the environmental effects of those exports, and thus no NEPA obligation stefnming from those effects. See Freeport, 827 F.3d at 47; accord Sabine Pass, 827 F.3d at 68-69; EarthReports, 828 F.3d at 956.

An agency has no obligation to gather or consider environmental information if it has no statutory authority to act on that information. That rule was the touchstone of Public Citizen, see 541 U.S. at 767-68, 124 S.Ct. 2204, and it distinguishes this *1373ease from the LNG-terminal trilogy. Contrary to our dissenting colleague’s view, our holding in the LNG cases was not based solely on the fact that a second agency’s approval was necessary before the environmental effect at issue could occur.8 Rather, Freeport and its companion cases rested on the premise that FERC had no legal authority to prevent the adverse environmental effects of natural gas exports. See Freeport, 827 F.3d at 47.

This raises the question: what did the Freeport court mean by its statement that FERC could not prevent the effects of exports? After all, FERC did have legal authority to deny an upgrade license for a natural gas export terminal. See Freeport, 827 F.3d at 40-41. And without such an upgrade license, neither gas exports nor their environmental effects could have occurred.

The answer must be that FERC was forbidden to rely on the effects of gas exports as a justification for denying an upgrade license. Cf. Motor Vehicle Mfrs. Ass’n of U.S. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (explaining that an agency acts arbitrarily and capriciously if it "makes a decision based on “factors which Congress had not intended it to consider”). The holding' in Freeport, then, turned not on the question “What activities does FERC regulate?” but instead on the question “"What factors can FERC consider when regulating in its proper sphere?” In the LNG cases, FERC was

Additional Information

Sierra Club v. Federal Energy Regulatory Commission | Law Study Group