Sierra Club v. Federal Energy Regulatory Commission
AI Case Brief
Generate an AI-powered case brief with:
Estimated cost: $0.001 - $0.003 per brief
Full Opinion
Opinion concurring in part and dissenting in part filed by Circuit Judge BROWN. â
Environmental groups and landowners have challenged the decision of the Federal Energy Regulatory Commission to approve the construction and operation of three new interstate natural-gas pipelines in the southeastern United States. Their primary argument is that the agencyâs assessment of the environmental impact of the pipelines was inadequate. We agree that FERCâs environmental impact statement did not contain enough information on the greenhouse-gas emissions that will result from burning the gas that the pipelines will carry. In all other respects, we conclude that FERC acted properly. We thus grant Sierra Clubâs petition âfor review and remand for preparation of a conforming environmental impact statement.
I
The Southeast Market Pipelines Project comprises three natural-gas pipelines now under construction in Alabama, Georgia, and Florida. The linchpin of the project is the Sabal Trail pipeline, which will wend its way from Tallapoosa County in eastern Alabama, across southwestern Georgia, and down to Osceola County, Florida, just south of Orlando:' a journey of nearly five hundred miles. Sabal Trail will connect the other two portions of the project. The firstâthe: Hillabee Expansionâwill boost the capacity of an existing pipeline in Alabama, which will feed gas to Sabal Trailâs upstream end for transport to Florida. At the downstream end of Sabal Trail will be the Florida Southeast Connection, which will link to a powĂ©r plant in Martin County, Florida, 120 miles away. Shorter spurs will join Sabal Trail to other proposed and existing power plants and pipeline networks. By its scheduled completion in 2021, the project will be able to carry over one billion cubic feet of natural gas per day.
The three segments of the project have different owners,
Despite these optimistic predictions, the project has drawn opposition from several quarters. Environmental groups fear that increased burning of natural gas will hasten climate change and its potentially catastrophic consequences. Landowners in the pipelinesâ path object to the seizure of their property by eminent domain. And communities on the projectâs route are concerned that pipeline facilities will be built in low-income and predominantly minority areas already overburdened by industrial polluters.
Section 7 of the Natural Gas Act places these disputes into the bailiwick of the Federal Energy Regulatory Commission (FERC), which has jurisdiction to approve or. deny the construction of interstate natural-gas pipelines. See 15 U.S.C. § 717f. Before any such pipeline can be built, FERC must grant the developer a âcertificate of public convenience and necessity,â id. § 717f(c)(l)(A), also called a Section 7 certificate, upon a finding that the project will serve the public interest, see id. § 717f(e). FERC is also empowered to attach âreasonable terms and conditionsâ to the certificate, as necessary to protect the public. Id. A certificate holder has the ability to acquire necessary rights-of-way from unwilling landowners by eminent domain proceedings. See id. § 717f(h).
FERC launched an environmental review of the proposed project in the fall of 2013. The agency understood that it would need to prepare an environmental impact statement (EIS) before approving the project, as the National Environmental Policy Act of 1969 (NEPA) requires for each âmajor Federal action[] significantly affecting the quality of the human environment.â See 42 U.S.C. § 4332(2)(C). FERC solicited public comment and held thirteen public meetings on the projectâs environmental effects, and made limited modifications to the project plan in response to public concerns, before releasing a draft impact statement in September 2015 and a final impact statement in December 2015. In the meantime, the pipeline developers formally applied for their Section 7 certificates in September and November 2014.
In the Certificate Order, issued on February 2, 2016, FERC granted the requested Section 7 certificates and approved construction of all three project segments, subject to compliance with various conditions not at issue here. Order Issuing Certificates and Approving Abandonment, Fla. Se. Connection, LLC, 154 FERC ¶ 61,080 (2016) (Certificate Order). This order recognized a number of parties as intervenors in the agency proceedings, among them three environmental groups (Sierra Club, Flint Riverkeeper, and Chattahoochee Riv-erkeeper) and two Georgia landowners whose land Sabal Trail will cross (GBA Associates and K. Gregory Isaacs). These parties timely sought rehearing and a stay of construction; FERC agreed to entertain their arguments but denied a stay. Construction on the pipelines began in August 2016. On September 7, 2016, FERC
Both the environmental groups (collectively, âSierra Clubâ) and the landowners timely petitioned our court for review of the Certificate Order and the Rehearing Order. Sierra Club argues that FERCâs environmental impact statement failed to adequately consider the projectâs contribution to greenhouse-gas emissions and its impact on low-income and minority communities. Sierra Club also contends that Sabal Trailâs service rates were based on an invalid methodology. The landowners allege further oversights in the EIS, dispute the public need for the project, and assert that FERC used an insufficiently transparent process to approve the pipeline certificates. Their petitions were consolidated before us.
II
We have jurisdiction to hear these petitions under the Natural Gas Act. See 15 U.S.C. § 717r(b). Any party to a proceeding under the Act who is âaggrievedâ by a FERC order may petition for review of that order in our court, provided that they first seek rehearing before FERC. Id. § 717r(a)-(b). Sierra Club was an interve-nor in the proceedings on all three pipeline applications, see Certificate Order App. A, and the landowner petitioners were inter-venors in the Sabal Trail proceedings, see id.
A party is âaggrievedâ by a FERC order if it challenges the order under NEPA and asserts an environmental harm. See Gunpowder Riverkeeper v. FERC, 807 F.3d 267, 273-74 (D.C. Cir. 2015). A landowner forced to choose between selling to a FERC-certified developer and undergoing eminent domain proceedings is also âaggrievedâ within the meaning of the Act. See B & J Oil & Gas v. FERC, 353 F.3d 71, 75 (D.C. Cir. 2004); Moreau v. FERC, 982 F.2d 556, 564 n.3 (D.C. Cir. 1993). Sierra Club falls into the former camp, and the Georgia landowners into the latter.
We also have an independent duty to ensure that at least, one petitioner has standing under Article III of the Constitution. See Ams. for Safe Access v. DEA, 706 F.3d 438, 442-43 (D.C. Cir. 2013). A petitioner invoking federal-court jurisdiction has the burden to establish that she has suffered an injury in fact that is fairly traceable to the challenged action of the defendant and âlikelyâ to be redressed by a favorable judicial decision. WildEarth Guardians v. Jewell, 738 F.3d 298, 305 (D.C. Cir. 2013). And an association, like Sierra Club, can sue on behalf of its members if at least one member would have standing to sue in her own right, the organization is suing to vindicate interests âgermane to its purpose,â and nothing about the claim asserted or the relief requested requires an individual member to be a party. Sierra Club v. FERC, 827 F.3d 36, 43 (D.C. Cir. 2016). On direct review of agency action, an association can establish its standing by having its individual members submit affidavits to accompany the associationâs opening brief. See Pub. Citizen, Inc. v. Natâl Highway Traffic Safety Admin., 489 F.3d 1279, 1289 (D.C. Cir. 2007).
Several individual Sierra Club members submitted such affidavits, explaining how the pipeline project would harm their âconcrete aesthetic and recreational interests.â WildEarth, 738 F.3d at 305. For example, one member, Robin Koon, explained that the Sabal Trail pipeline will cross his property (on an easement taken by eminent domain), that con
Because they allege concrete injury from FERCâs order certifying the pipeline project, and because that certification was based on an allegedly inadequate environmental impact statement, these Sierra. Club members, and therefore Sierra Club itself, have standing to object to any deficiency in the environmental impact statement.
Transco, owner of the Hillabee Expansion, argues that no Sierra Club member has alleged an injury caused by Tran-scoâs section of the overall project, which would suggest â that Sierra Club lacks standing to seek the vacatur of Hillabeeâs certificate. Transco thus implicitly argues that the Certificate Order is- severable. Under this view, if Sierra Club succeeds on the merits, but has standing to challenge only Sabal Trailâs certificate, we could vacate only the portion of the Certificate Order pertaining to Sabal Trail, and leave the rest intact.
The question whether an agency order is severable turns on the agencyâs intent. See Epsilon Elecs., Inc. v. U.S. Depât of Treasury, 857 F.3d 913, 929 (D.C. Cir. 2017). âWhere 'there is substantial doubt that the agency would have adopted the same disposition regarding the unchallenged portion if the challenged portion were subtracted, partial affirmance is improper,â Id. (quoting North Carolina v. FERC, 730 F.2d 790, 795-96 (D.C. Cir. 1984)). Since the beginning of its environmental review, FERC has treated the project as a single, integrated proposal. See Notice of Intent to Prepare an Environmental Impact Statement for the Planned Southeast Market Pipelines Project, 79 Fed. Reg. 10,793, 10,794 (Feb. 26, 2014)
We substantially doubt that FERC would have approved the Southeast Market Pipelines Project only in part, and we especially doubt that. the agency would have certified either of the other two segments if Sabal Trail were not part of the project. Because Sierra Club and the landowners have alleged injury-in-fact caused by Sabal Trail, and because the Certificate Order is not severable, both sets of petitioners have standing to challenge the Certificate Order as a whole.
Having concluded that we have jurisdiction to entertain all of petitionersâ claims, we turn to the merits of those claims.
Ill .
Both sets of petitioners rely heavily on the National Environmental . Policy Act of 1969, Pub. L. No. 91-190, 83 Stat. 852 (1970). NEPA âdeclares a broad national commitment to protecting and promoting environmental quality,â and brings that commitment to bear on the operations of the federal government. Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 348, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989). The statute âcommands agencies to imbue their decisionmaking, through, the use of certain procedures, with our countryâs commitment to environmental salubrity.â Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190, 193-94 (D.C. Cir. 1991). One of the most important procedures NEPA mandates is the preparation, as part of every âmajor Federal aetion[] significantly affecting the quality of the human environment,â of a âdetailed statementâ discussing and disclosing the environmental impact of the action. 42 U.S.C. § 4332(2)(C).
This environmental impact statement, as it has come to be called, has two purposes. It forces the agency to take a âhard lookâ at the environmental consequences of its actions, including alternatives to its proposed course. See id. § 4332(2) (C) (iii); Balt. Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 462 U.S. 87, 97, 103 S.Ct. 2246, 76 L.Ed.2d 437 (1983). It also ensures that these environmental consequences, and the agencyâs consideration of them, are disclosed to the public. See WildEarth Guardians, 738 F.3d at 302. Importantly, though, NEPA âdirects agencies only to look hard at the environmental effects of their decisions, and not to take one type of action or another.â Citizens Against Burlington, 938 F.2d at 194, That is, the statute is primarily information-forcing.
The role of the courts in reviewing agency compliance with NEPA is accordingly limited. Furthermore, because NEPA does not create a private right of action, we can entertain NEPA-based challenges only under the Administrative Procedure Act and its deferential standard of review. See Theodore Roosevelt Conservation Pâship v. Salazar, 616 F.3d 497, 507 (D.C. Cir. 2010), That is, our mandate âis âsimply to ensure that the agency has adequately considered and disclosed the environmental impact of its actions and that, its decision is not arbitrary or capricious.ââ WildEarth Guardians, 738 F.3d at 308 (quoting City of Olmsted Falls v. FAA, 292
But at the same time, we are responsible for holding agencies to the standard the statute establishes. An EIS is deficient, and the agency action it un-dergirds is arbitrary and capricious, if the EIS does not contain âsufficient discussion of the relevant issues and opposing viewpoints,â Nevada, 457 F.3d at 93 (quoting Nat. Res. Def. Council v. Hodel, 865 F.2d 288, 294 (D.C. Cir. 1988)), or if it does not demonstrate âreasoned decision-making,â Del. Riverkeeper Network v. FERC, 753 F.3d 1304, 1313 (D.C. Cir. 2014) (quoting Found. on Econ. Trends v. Heckler, 756 F.2d 143, 154 (D.C. Cir. 1985)). The overarching question is whether an EISâs deficiencies are significant enough to undermine informed public comment and informed decisionmaking. See Nevada, 457 F.3d at 93. This is NEPAâs ârule of reason.â See Depât of Transp. v. Pub. Citizen, 541 U.S. 752, 767, 124 S.Ct. 2204, 159 L.Ed.2d 60 (2004).
With those principles in mind, we direct our attention to the specific deficiencies the petitioners have alleged in the EIS for the Southeast Market Pipelines Project. As noted above, FERC prepared a single unified EIS for the projectâs three pipelines, and no party has challenged that approach. Thus, for purposes of our NEPA analysis, we will consider the project as a whole.
A
The principle of environmental justice encourages agencies to consider whether the projects they sanction will have a âdisproportionately high and adverseâ impact on low-income and predominantly minority communities.
Sierra Club argues that the EIS failed to adequately take this principle into account. Like the other components of an EIS, an environmental justice analysis is measured against the arbitrary-and-capricious standard. See Cmtys. Against Runway Expansion, Inc. v. FAA, 355 F.3d 678, 689 (D.C. Cir. 2004).
The EIS explained that 83.7% of the pipelinesâ proposed route would cross
FERC concluded that the various feasible alternatives âwould affect a relatively similar percentage of environmental justice populations,â and that the preferred route thus would not have a disproportionate impact on those populations. See J.A. 836. The agency also independently concluded that the project would not have a âhigh and adverseâ impact on any population,- meaning, in the agencyâs view, that it could not have a âdisproportionately high and adverseâ impact on any population, marginalized or otherwise.
Sierra Club contends that FERC misread âdisproportionately high and adverse,â the standard for when a particular environmental effect raises an environmental-justice concern. By Sierra Clubâs lights, any effect can -fulfill the test, regardless of its intensity, extent, or duration, if it is not beneficial and falls disproportionately on environmental-justice communities. But even if we assume that understanding to be correct, we cannot see how this EIS was deficient. It discussed the intensity, extent, and duration of the pipelinesâ environmental effects, and also separately discussed the fact that those effects will disproportionately fall on environmental-justice communities. Recall that the EIS informed readers and the agencyâs ultimate decisionmakers that 83.7% of the pipelinesâ length would be in or near environmental-justice communities. The EIS also evaluated route alternatives in part by looking at the number of environmental-justice communities each would cross,' and the mileage of pipeline each would place in low-income and minority areas. FERC thus grappled with the disparate impacts of the various possible pipeline routes. Perhaps Sierra Club would have a stronger claim if the agency had refused entirely to discuss the demographics of the populations thĂĄt will feel the pipelinesâ effects, and had justified this refusal by pointing to the limited intensity, extent, and duration of those effects. However, as the EIS stands, we see no deficiencies serious enough to defeat the statuteâs goals of fostering well-informed decisionmaking and public comment. See Nevada, 457 F.3d at 93.
The same goes for Sierra Clubâs other arguments. The agencyâs methodology was reasonable, even where it deviated from what Sierra Club would have preferred. See Runway Expansion, 355 F.3d at 689. Take the agencyâs decision to compare the demographics along the various proposed routes to each other instead of âthe gener
Sierra Club is particularly concerned about Sabal Trailâs plan to build a compressor .station (a facility that helps âpumpâ gas along the pipeline, and gives off ah- and noise pollution while doing so) in an African American neighborhood of Albany, Dougherty County, Georgia. The agency identified environmental-justice communities by looking at the demographics of census tracts, which are county subdivisions created to organize census data. The neighborhood in question is a 100% African American census block, an even smaller census subdivision, but because it sits in the midst .of a majority-white census tract, FERC did not designate it an environmental-justice community. Sierra Clubâs objection to this omission elevates form over substance. The goal of an environmental-justice analysis is satisfied if an agency recognizes and discusses a projectâs impacts on predominantly-minority communities, even if it does not formally label each such community an âenvironmental justice community.â FERC did recognize the existence and demographics of the neighborhood in question, and discussed the neighborhood extensively. The EIS listed community features, including subdivisions, schools, and churches, along with their distances from the proposed compressor station, and explained that the stationâs noise and air-quality effects on these locations were expected to remain within acceptable limits.
More persuasive is Sierra Clubâs argument that FERC disregarded the extent to which Dougherty County is already overburdened with pollution sources. A letter to FERC from four members of Georgiaâs congressional delegation cites the grim statistics: southern Dougherty County has 259 hazardous-waste facilities, 78 air-polluting facilities, 20 toxic-polluting facilities, and- 16 water-polluting facilities. The EIS did not mention these existing polluters in its discussion of Dougherty County. Sierra Club thus argues that FERC inadequately considered the projectâs âcumulative impacts,â that is, its effects taken in combination with existing environmental hazards in the same area. See 40 C.F.R. § 1508.7; Del Riverkeeper, 753 F.3d at 1319-20.
Perhaps FERC could have said, more, but the discussion it undertook of the cumulative impacts of the proposed route fulfilled NEPAâs goal of guiding informed decisionmaking. The EIS acknowledged that the Sabal Trail project will generate ah* pollution and noise pollution in Albany, and it projected cumulative levels of both of these types of pollution from all sources in the vicinity of the compressor station, finding that both would remain below harmful thresholds.
To sum up, the EIS acknowledged and considered the substance of all the concerns Sierra Club now raises: the fact that the Southeast Market Pipelines Project will travel primarily through low-income and minority communities, and the impact of the pipeline on the city of Albany and Dougherty County in particular. The EIS also laid out a variety of alternative approaches with potential to address those concerns, including those proposed by, petitioners, and explained why, in FERCâs view, they would do more harm than good. The EIS also gave the public and agency decisionmakers the qualitative and quantitative tools they needed to make an informed choice for themselves. NEPA requires nothing more.
'S
Itâs not just the journey, though, itâs also the destination. All the natural' gas that will travel through these pipelines will be going somewhere: specifically, to power plants in Florida, some of which already exist, others of which are in the planning stages. Those power plants will burn the gas, generating both electricity and carbon dioxide. And once in the atmosphere, that carbon dioxide will add to the greenhouse effect, which the EIS describes as âthe primary contributing factorâ in global climate change. J.A. 915. The next question before us is whether, and to what extent, the EIS for this pipeline project needed to discuss these âdownstreamâ effects of the pipelines and their cargo. We conclude that at a minimum, FERC should have estimated the amount of power-plant carbon emissions that the pipelines will make possible.
An agency conducting a NEPA review must consider not only the direct effects, but also the indirect environmental effects, of the project under consideration. See 40 C.F.R. § 1502.16(b). âIndirect effectsâ are those that âare caused by the [project] and are later in time or farther removed in distance, but are still reasonably foreseeable.â Id, § 1508.8(b). The phrase âreasonably foreseeableâ is the key here. Effects are reasonably foreseeable if they are âsufficiently likely to occur that a person of ordinary prudence would take [them] into account in reaching a decision,â EarthReports, Inc. v. FERC, 828 F.3d 949, 955 (D.C. Cir. 2016) (citation omitted).
What are the âreasonably foreseeableâ effects of authorising a pipeline that will
The pipeline developers deny that FERC would be the legally relevant cause of any power plant carbon emissions, and thus contend that FERC had no obligation to consider those emissions in its NEPA analysis. They rely on Department of Transportation v. Public Citizen, 541 U.S. 752, 124 S.Ct. 2204, 159 L.Ed.2d 60 (2004), a case involving the Federal Motor Carrier Safety Administrationâs development of safety standards for Mexican trucks operating in the United States. The agency had proposed those standards because the President planned to lift a moratorium on Mexican motor carriers operating in this country. These standards would require roadside inspections, which had the potential to create adverse environmental effects. The agencyâs EIS discussed the effects of these roadside inspections, but Public Citizen contended that the EIS was also required to address the environmental effects of increased truck traffic between the two countries. See id. at 765, 124 S.Ct. 2204.
The Supreme Court sided with the agency. The Court noted that the agency would have no statutory authority to exclude Mexican trucks from the United States once the President lifted the moratorium; it would only have power to set safety rules for those trucks. See id. at 766-67, 124 S.Ct. 2204. And because the agency could not exclude Mexican trucks from the United States, it would have no reason to gather data about the environmental harms of admitting them. The purpose of NEPA is to help agencies and the public make informed decisions. But when the agency has no legal power to prevent a certain environmental effect, there is no decision to inform, and the agency need not analyze the effect in its NEPA review. See id. at 770, 124 S.Ct. 2204.
We recently applied the Public Citizen rule in three challenges to FERC decisions licensing liquefied natural gas (LNG) terminals. See Sierra Club v. FERC (Freeport), 827 F.3d 36 (D.C. Cir. 2016); Sierra Club v. FERC (Sabine Pass), 827 F.3d 59 (D.C. Cir. 2016); EarthReports, Inc. v. FERC, 828 F.3d 949 (D.C. Cir. 2016). Companies can export natural gas from the United States through an LNG terminal, but such natural gas exports require a license from the Department of Energy. See Freeport, 827 F.3d at 40. They also require physical upgrades to a terminalâs facilities. The Department of" Energy has delegated to FERC the authority to license those upgrades. See id. A question presented to us in all of theseâcases was whether FERC, in licensing physical upgrades for an LNG terminal, needed to evaluate the climate-change effects of exporting natural gas. Relying on Public Citizen, we answered no in each case. FERC had no legal authority to consider the environmental effects of those exports, and thus no NEPA obligation stefnming from those effects. See Freeport, 827 F.3d at 47; accord Sabine Pass, 827 F.3d at 68-69; EarthReports, 828 F.3d at 956.
An agency has no obligation to gather or consider environmental information if it has no statutory authority to act on that information. That rule was the touchstone of Public Citizen, see 541 U.S. at 767-68, 124 S.Ct. 2204, and it distinguishes this
This raises the question: what did the Freeport court mean by its statement that FERC could not prevent the effects of exports? After all, FERC did have legal authority to deny an upgrade license for a natural gas export terminal. See Freeport, 827 F.3d at 40-41. And without such an upgrade license, neither gas exports nor their environmental effects could have occurred.
The answer must be that FERC was forbidden to rely on the effects of gas exports as a justification for denying an upgrade license. Cf. Motor Vehicle Mfrs. Assân of U.S. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983) (explaining that an agency acts arbitrarily and capriciously if it "makes a decision based on âfactors which Congress had not intended it to considerâ). The holding' in Freeport, then, turned not on the question âWhat activities does FERC regulate?â but instead on the question â"What factors can FERC consider when regulating in its proper sphere?â In the LNG cases, FERC was