AI Case Brief
Generate an AI-powered case brief with:
Estimated cost: $0.001 - $0.003 per brief
Full Opinion
Appellant CSR West breached a contract to supply fill for land development. Issues on appeal include the calculation of damages based on âhypothetical coverâ; the allowance of prejudgment interest; and the denial of the plaintiffâs requests to include sales tax and consequential damages in the award of damages. We affirm in all respects.
According to unchallenged findings of fact entered after a bench trial, Robert Egerer owned a 10-acre parcel of land in Skagit County that he planned to develop into commercial property. The property required a considerable amount of fill to make it suitable for development.
Egerer first purchased fill material in 1995, when he contracted at the rate of $1.10 per cubic yard to have Wilder Construction haul to his property some material being excavated from the shoulders of Interstate 5 as a part of a highway improvement project. In its suitability to serve as structural fill, the shoulder material resembled a gravel known as âpit run,â but it was cheaper than pit run because it contained asphalt grindings.
Beyond what Wilder Construction could supply, Egerer needed roughly 17,000 cubic yards of fill material. In May 1997, Egerer learned that CSR West had contracted with the Washington State Department of Transportation to excavate material from the shoulder areas of Interstate 5 near Lake Samish. He met with John Grisham, CSRâs sales manager, and they reached an agreement to have CSR transport âallâ the shoulder excavations from the project to Egererâs site at the rate of $.50 per cubic yard.
CSR brought fill material to Egererâs property on only two nights: July 9 and 10, 1997. Shortly thereafter, the Department of Transportation issued a change order that allowed CSR to use the excavated shoulder material in the reconstruction of the shoulder area. It was more profitable for CSR to supply the material for the Stateâs use than to fulfill its contract with Egerer. CSR excavated a total of 16,750 cubic yards of material during its work on the shoulder project in 1997 and supplied virtually all of it to the Department of Transportation.
Egerer did not purchase replacement fill at the time of the breach in July 1997. Asked about this at trial, he explained that it would have been too expensive, and he also did not think there was time to find replacement fill
In the summer of 1999, Egerer learned of an unexpected landslide at a gravel pit not far from his property. The company agreed to sell Egerer the unwanted slide material at a cost of $6.39 per cubic yard, including the cost of hauling and spreading.
Egerer filed suit in November 2000, alleging that CSR breached its contract by failing to deliver all the excavated shoulder material in the summer of 1997. After a bench trial, the court found breach. The court then turned to the Uniform Commercial Code to determine the measure of damages. CSR raises several legal issues with respect to the award of damages.
The findings, which are unchallenged, are deemed verities on appeal. We review conclusions of law de novo to see if they are supported by the trial courtâs findings of fact. Bingham v. Lechner, 111 Wn. App. 118, 127, 45 P.3d 562 (2002).
Where a seller fails to make delivery of goods sold to a buyer, the buyer has two alternative remedies under the Uniform Commercial Code (U.C.C.). One is the remedy of âcoverâ: the buyer may purchase substitute goods and recover as damages the difference between the cost of this cover and the contract price, provided the buyer covers in good faith and without unreasonable delay. RCW 62A. 2--712. The other, a complete alternative, is damages for nondelivery, also known as âhypothetical coverâ:
The court determined that Egerer was limited to damages for nondelivery under section 2-713: âMr. Egerer is limited to damages reflecting the difference between CSR contract price and the price he could have obtained replacement material for at the time of the breach in 1997. See RCW 62A.2-713(1) and Comment 3.â
CSR accepts the trial courtâs decision to apply the remedy furnished by section 2-713, but contends the court erred by calculating damages based on a market price of $8.25 per cubic yard for pit run. CSR argues that $8.25 was not âthe price for goods of the same kindâ (as U.C.C. comment 2 calls for) because pit run is a product superior to shoulder excavations containing asphalt grindings. CSR further argues that $8.25 was not âthe market price at the time when the buyer learned of the breachâ (as RCW 62A.2-713 calls for) because the breach was in July 1997 and the $8.25 price was as of six months later â in January, 1998. CSR takes the position that the trial court should instead have used the $1.10 per cubic yard price reflected in Egererâs 1995
The trial court expressly relied on comment 3 to U.C.C. 2-713 in determining that $8.25 per cubic yard was the price for which Egerer could have obtained replacement material at the time of the breach. That comment states in part, âWhen the current market price under this section is difficult to prove the section on determination and proof of market price is available to permit a showing of a comparable market price or, where no market price is available, evidence of spot sale prices is proper.â U.C.C. cmt. 3, RCWA 62A.2-713. The section on determination and proof of market price provides,
If evidence of a price prevailing at the times or places described in this Article is not readily available the price prevailing within any reasonable time before or after the time described or at any other place which in commercial judgment or under usage of trade would serve as a reasonable substitute for the one described may be used, making any proper allowance for the cost of transporting the goods to or from such other place.
RCW 62A.2-723(2).
A court is granted a âreasonable leewayâ in measuring market price under RCW 62A.2-723. Sprague v. Sumitomo Forestry Co., 104 Wn.2d 751, 760, 709 P.2d 1200 (1985). Contrary to CSRâs argument, a trial court may use a market price for goods different in quality from those for which the buyer contracted. That possibility is encompassed in the reference to âprice . . . which in commercial judgment or under usage of trade would serve as a reasonable substitute for the one described.â And RCW 62A.2-723 expressly permits looking to a price âprevailing within any reasonable time before or after the time described.â
We conclude the trial court did not misapply the law in concluding that the January 1998 price for pit run was the relevant market price. The court found the 1998 quotes for
Egerer, in his cross-appeal, argues that the relevant market price was much higher. He contends the trial court should have based its calculation of damages on figures showing that the Washington Department of Transportation was paying CSR between $33.33 and $46.80 per cubic yard for gravel pit material at that time. But the record does not indicate that Egerer made any argument below based on figures in CSRâs contract with the State, and we will not consider it for the first time on appeal.
PREJUDGMENT INTEREST
The court determined that Egerer was entitled to prejudgment interest totaling $70,098.75, calculated at the statutory rate âbeginning in July 1997 when CSR retained profits from the breach.â
Prejudgment interest is awardable for a liquidated claim. Prier v. Refrigeration Engâg Co., 74 Wn.2d 25, 32, 442 P.2d 621 (1968). A claim is liquidated where âthe evidence furnishes data which, if believed, makes it possible to compute the amount with exactness, without reliance on opinion or discretion.â Prier, 74 Wn.2d at 32 (citing Charles T. McCormick, Handbook on the Law of Damages § 54, at 213 (1935)). A claim is unliquidated âwhere the exact amount of the sum to be allowed cannot be definitely fixed from the facts proved, disputed or undisputed, but must in the last analysis depend upon the opinion or discretion of the judge or jury as to whether a larger or a smaller amount should be allowed.â Prier, 74 Wn.2d at 33 (quoting McCormick, supra, § 54, at 216).
CSR argues that Egererâs claim required the trial court, as fact finder, to exercise discretion in deciding to use the January 1998 price of pit run as the market price, rather than the actual price Egerer paid for landslide gravel in the summer of 1999 or the Wilder contract price for shoulder excavations.
The fact that a claim is disputed does not render the claim unliquidated, so long as it may be determined by reference to an objective source such as fair market value. Aker Verdal A/S v. Neil F. Lampson, Inc., 65 Wn. App. 177, 190, 828 P.2d 610 (1992). âHowever, when determining the measure of damages requires the exercise of discretion by the factfinder, the claim is unliquidated.â Aker Verdal A/S, 65 Wn. App. at 191 (plaintiff made in-house repairs to part of damaged crane, and jury decided to measure damage as the internal cost of labor and materials rather than as the rate plaintiff could have charged the customer if crane had not collapsed; held, cost of in-house repair was unliquidated). See also Maryhill Museum of Fine Arts v. Emilâs Concrete Constr. Co., 50 Wn. App. 895, 903, 751 P.2d
Unlike in Aker Verdal A/S and Maryhill Museum of Fine Arts, here the measure of damages to be used was not left to the discretion of the fact-finder; it was fixed by statute as the difference between the contract price and the prevailing market price at the time of the breach. The facts are more like those in Dautel v. Heritage Home Center, Inc., 89 Wn. App. 148, 948 P.2d 397 (1997), review denied, 135 Wn.2d 1003 (1998). In that case, the plaintiff sued for back wages, including unpaid commissions. The trial court found the plaintiff was owed a 20 percent commission on two transactions rather than a 10 percent commission, as the employer contended. On appeal, this court held that the trial court had erroneously refused to award prejudgment interest:
Regarding the claim for unpaid commissions, the dispute between the parties related to the proper percentage Dautel was entitled to be paid. The amount actually owing could be computed with exactness once the trial court determined that Dautel was entitled to her full commission rate of 20 percent. Therefore, the amount was a liquidated sum.
Dautel, 89 Wn. App. at 155.
Like Dautel, where the trial court exercised discretion only to find the appropriate commission percentage, the trial court here exercised discretion only to find the appropriate market price. The amount CSR actually owed could be computed with exactness once the trial court found that $8.25 per cubic yard was the market price at the time Egerer learned of CSRâs breach.
CSR cites authority stating that a defendant should not be required to pay prejudgment interest in cases where the defendant is unable to ascertain the amount owed to the plaintiff. Aker Verdal A/S, 65 Wn. App at 189 (citing Hansen v. Rothaus, 107 Wn.2d 468, 473, 730 P.2d 662
Where this is so, while the person who is charged with the duty of paying this valuation could probably not have known when the duty to pay arose, with entire exactness, the precise figure at which the value would be fixed, he could have estimated it within a narrow range of possible variation.
McCormick, supra, § 55, at 218.
That CSR proposed a lower market price does not render the claim unliquidated. The fact finder believed evidence showing that $8.25 was the market price, and that evidence made it possible to compute exact damages without reliance on opinion or discretion. See Prier, 74 Wn.2d at 32.
CSR further argues that prejudgment interest, if awardable, should accrue from the time Egerer bought replacement fill in June 1999, not â as the trial court concluded â from the time of the breach in 1997. CSR cites authority stating that an injured party âshould be compensated for the âuse valueâ of money it was forced to spend to cover its loss.â Aker Verdal A/S, 65 Wn. App. at 189. CSR reasons that Egerer did not lose the use value of money until he actually made a replacement purchase in June of 1999 and that an award of prejudgment interest before that date constitutes a windfall for Egerer because it compensates him for the use of his money during a time when he still retained its use.
This is not, however, a case where damages were measured by the differences between the cost of cover and the contract price. Egererâs purchase in June 1999 was not cover. His damages were measured as âthe difference between the market price at the time the buyer learned of the
If the breach consists of a failure to pay a definite sum in money or to render a performance with fixed or ascertainable monetary value, interest is recoverable from the time for performance on the amount due less all deductions to which the party in breach is entitled.
Restatement (Second) of Contracts § 354, at 150 (1981). The comment to this section states:
This Section deals with an injured partyâs right to interest as damages in compensation for the deprivation of a promised performance. Had the performance been rendered when it was due, the injured party would have been able to make use of it. Interest is a standardized form of compensation to the injured party for the loss of that use ....
Restatement (Second) of Contracts § 354 cmt. a (1981).
CSR promised to supply fill to Egerer at a price he could afford. The breach deprived him of the opportunity to advance his development plans in the summer of 1997 because, as the record indicates, cheap fill is rarely available. We conclude that the trial court properly selected July 1997, the date of breach, as the initiation point for the award of prejudgment interest.
SALES TAX
Egerer contends in his cross-appeal that the trial court erred by refusing to include in his damages the sales tax he would have paid had he actually covered. An award of damages may include an amount for sales tax
CONSEQUENTIAL DAMAGES
Egerer also challenges the trial courtâs denial of his request for consequential damages. He sought consequential damages in the form of lost rents for a period of 24 months, on the theory that CSRâs breach caused a two-year delay in completion of the commercial building space.
A buyer may recover consequential damages resulting from a sellerâs breach where the loss results from general or particular needs of the buyer that the seller had reason to know about at the time of contracting. RCW 62A.2-715(2), (2)(a). The trial court concluded that CSR did not have reason to know of Egererâs requirements or needs at the time it entered into the contract. The unchallenged findings of fact amply support this conclusion. While Egerer may have had prospective tenants in the summer of 1997, he ânever told anyone at CSR about the prospective tenants for his building.â Egerer âdid not discuss any specific detailsâ about his development plans during his meeting in June 1997 with CSRâs sales manager, Grisham. And he ânever discussed with anyone from CSR a time line for development of his site.â
Affirmed.
Cox and Schindler, JJ., concur.
Allied Canners & Packers, Inc. v. Victor Packing Co., 162 Cal. App. 3d 905, 911-12, 209 Cal. Rptr. 60, 61 (1984).
Clerkâs Papers at 30.
Finding of Fact 83.
Verbatim Report of Proceedings at 104.
Clerkâs Papers at 30.
Clerkâs Papers at 30.
Findings of Fact 64, 66, 67; Clerkâs Papers at 26.