Full Opinion
delivered the opinion of the Court.
A water supply corporation sued a city and the cityâs contractors after the contractors installed sewer lines above portions of the corporationâs water system. A jury found that the city breached its contract with the water supply corporation and that the contractors were negligent. The court of appeals disagreed, rendering a take-nothing judgment against the water
I. Factual and Procedural Background
Alton is a municipality located in Hidal-go County. Sharyland Water Supply Corporation is a non-profit rural water supply corporation with offices in Mission, which is also in Hidalgo County. In the early 1980s, Alton constructed a potable water distribution system for its residents.
In 1994, Alton received federal and local grants to install a sanitary sewer system,
A year later, Sharyland sued Alton for breaching the Water Supply Agreement, alleging that Sharyland suffered significant injury because Altonâs sanitary sewer residential service connections were negligently installed in violation of state regulations and industry standards. Id. at 140. In particular, Sharyland claimed that the location and proximity of the sewer fines to the water system threatened to contaminate Sharylandâs potable water supply. Id. Alton counterclaimed, seeking a declaration that the Water Supply Agreement was void. Sharyland also sued the contractors for negligence and breach of contract, contending it was a third party bene-
Alton filed a jurisdictional plea asserting immunity from suit. The trial court denied the plea, and the court of appeals affirmed in a pre-Tooke decision holding that Local Government Code section 51.013âs âsue and be suedâ language waived immunity. City of Alton v. Sharyland Water Supply Corp., 145 S.W.3d 673, 681 (Tex.App.-Corpus Christi 2004, no pet.); see also Tex. Loc. Govât Code § 51.013; Tooke v. City of Mexia, 197 S.W.3d 325, 328-29 (Tex.2006) (holding that âsue and be suedâ and âplead and be impleadedâ did not clearly and unambiguously waive immunity). Alton did not petition this Court for review of that decision.
Back in the trial court, Sharyland successfully moved for summary judgment on Altonâs counterclaim. The trial court also granted Sharylandâs motion seeking a judgment declaring that Chapter 30, section 317.13 of the Texas Administrative Code (requiring, among other things, certain minimum distances between potable water and sanitary sewer lines) governed the sewer lines at issue in this case. 277 S.W.3d at 141.
The remaining claims were tried to a jury, which found that Alton breached the Water Supply Agreement, that each of the three contractors breached their contracts with Alton, and that Sharyland was a third party beneficiary of those contracts. The jury also found that the contractorsâ negligence injured Sharyland. The jury awarded identical damages for each of the three claims: $14,000 in past damages and $1,125,000 in future damages. The jury also found that Sharyland had incurred reasonable attorneyâs fees for trial and appeal. The trial court rendered judgment for Sharyland against Alton and the contractors, jointly and severally, and denied Sharylandâs request for injunctive relief to compel Alton to bring the sewer system into compliance with Administrative Code section 317.13.
As to Alton, the court of appeals held that Chapter 271 of the Local Government Code waived immunity on Sharylandâs contract claim. 277 S.W.3d at 144; see also Tex. Loc. Govât Code § 271.152 (waiving immunity for certain contract claims against local government entities). Nonetheless, the court held that the damages awarded were not for a âbalance due and owedâ nor for âchange orders or additional work,â and thus were not within the scope of damages allowed by statute. 277 S.W.3d at 146 (citing Tex. Loc. Govât Code § 271.153). The appellate court rejected Sharylandâs arguments that an equitable waiver-by-conduct exception to immunity applied or that Altonâs counterclaim negated immunity. Id. at 143. Although the court of appeals concluded that Sharyland could not recover attorneyâs fees on its contract claim against Alton, the court held that Sharyland could, on remand, segregate and attempt to recover fees attributable to its declaratory judgment on the applicability of Administrative Code section 317.13. Id. at 147-48.
As to the contractors, the court of appeals held that the economic loss rule barred Sharylandâs negligence claim. Id. at 155. The court concluded that Shary-land was not a third party beneficiary of Altonâs agreement with the contractors, and therefore could not recover either damages or attorneyâs fees for the contractorâs breach. Id. The court affirmed the trial courtâs denial of Sharylandâs request for equitable relief but reversed the remainder of the judgment, rendering judgment that Sharyland take nothing as to everything but its attorneyâs fees claim for the declaratory judgment. Id. at 158. We
II. Sharylandâs claims against Alton
Alton asserts that it is immune from Sharylandâs claims. For several reasons, Sharyland disagrees. First, Sharyland argues, Local Government Code chapter 271 waives Altonâs immunity from suit. Second, even if chapter 271 is inapplicable, Alton is not entitled to immunity on claims that are germane to, connected with, and properly defensive to its counterclaim. See Reata Constr. Corp. v. City of Dali, 197 S.W.3d 371 (Tex.2006). Finally, Sha-ryland asks us to recognize an equitable waiver of immunity, given the extent of Altonâs purported misconduct and the threat to public health.
A. Waiver of immunity under Local Government Code section 271.152
Local Government Code section 271.152 provides a limited waiver of immunity for local governmental entities that enter into certain contracts. Tex. Loc. Govât Code § 271.152. To come within the waiver, the contract must be in writing, properly executed, and must state âthe essential terms of the agreement for providing goods or services to the local governmental entity.â Id. § 271.151. As the court of appeals noted, no one disputes that the agreements in this case involve services. 277 S.W.3d at 144. Nor does Alton dispute that section 271.152 applies to its contract with Sharyland. Therefore, the court of appeals correctly concluded that section 271.152 waived Altonâs immunity. Id.
B. Damages under Local Government Code section 271.153
We next determine whether Shary-land may recover under Local Government Code section 271.153, which limits damage awards against local governmental entities. See Tex. Loc. Govât Code § 271.153(a). Sharyland sought to recover the costs to repair its system, and the court of appeals held that section 271.153(a) prohibits the recovery of money damages for these alleged injuries. 277 S.W.3d at 146. Id. We agree.
Section 271.153 limits â[t]he total amount of money awarded in an adjudication brought against a local governmental entity for breach of a contract subject to [subchapter I of chapter 271].â Tex. Loc. Govât Code § 271.153(a). The provision specifies that recovery is limited to:
(1) the balance due and owed by the local governmental entity under the contract as it may have been amended, including any amount owed as compensation for the increased cost to perform the work as a direct result of owner-caused delays or acceleration;
(2) the amount owed for change orders or additional work the contractor is directed to perform by a local governmental entity in connection with the contract; and
(3) interest as allowed by law.
Id.
*413 (1) consequential damages, except as expressly allowed under Subsection (a)(1);
(2) exemplary damages; or
(3) damages for unabsorbed home office overhead.
Id. § 271.153(b). The court of appeals concluded that section 271.153(a) âdoes not provide Sharyland an avenue for recovery.â 277 S.W.3d at 146. The kind of damages sought by Sharyland were not those provided for or contemplated in the Water Supply Agreement and are not a âbalance due and owedâ under that contract. Nor are these costs the âdirect result of owner-caused delays or acceleration,â or the âamount owed for change orders or additional work the contractor [was] directed to perform by [the] local governmental entity in connection with the contract.â Tex. Loc. Govât Code § 271.153(a). A plain reading of the statute negates recovery under this chapter. See, e.g., Hernandez v. Ebrom, 289 S.W.3d 316, 318 (Tex.2009); Morrison v. Chan, 699 S.W.2d 205, 208 (Tex.1985).
C. Waiver of immunity by counterclaim
Sharyland also argues that Alton is not entitled to immunity because it filed a counterclaim seeking affirmative relief. The court of appeals held that because Altonâs counterclaim merely asked for a declaration that the Water Supply Agreement was void, without an accompanying claim for monetary damages, Alton did not waive its immunity. 277 S.W.3d at 143.
Sharyland contends that the court of appeals erred in holding that only counterclaims for monetary damages deprive Alton of immunity. Sharyland asserts that a rescission counterclaim that would transfer a valuable asset should fall within Reata!s offset holding as well. Sharyland argues that Altonâs counterclaim sought affirmative relief because it demanded that Shary-land be divested of valuable property by requesting that the trial court rescind Sha-rylandâs easements and award a portion of the Sharyland Water supply system to Alton.
We need not decide whether Sharylandâs argument is viable, however. Even assuming that it is, under our recent precedent, Sharyland could not recover against Alton once its sole counterclaim was defeated on summary judgment. In Reata Construction Corp. v. City of Dallas, we held that âwhen an affirmative claim for relief is filed by a governmental entity, ... immunity from suit no longer completely exists for the governmental entity.â Reata, 197 S.W.3d 371, 376 (Tex.2006). We reasoned that
where the governmental entity has joined into the litigation process by asserting its own affirmative claims for monetary relief, we see no ill befalling the governmental entity or hampering of its governmental functions by allowing adverse parties to assert, as an offset, claims germane to, connected with, and properly defensive to those asserted by the governmental entity.
Id. at 376-77. Shortly after Reata, we held that a city âdoes not have immunity from suit for claims germane to, connected with, and properly defensive to its counter
Altonâs counterclaim was short-lived; the trial court held that it was barred by section 1926(b) of title 7 of the United States Code. 277 S.W.3d at 141; see also 7 U.S.C. § 1926(b).
D. Equitable waiver
Finally, Sharyland asserts that a party can waive immunity by conduct. It points to a footnote in Federal Sign v. Texas Southern University, 951 S.W.2d 401, 408 n. 1 (Tex.1997), in which we observed that there may be circumstances âwhere the State may waive its immunity by conduct other than simply executing a contract.â Five years after Federal Sign, however, we rejected the invitation to recognize such a waiver, holding that it was generally the Legislatureâs province to waive immunity. Tex. Natural Res. Conservation Commân v. IT-Davy, 74 S.W.3d 849, 857 (Tex.2002). We noted that â[treating a waiver-by-conduct exception would force the State to expend its resources to litigate the waiver-by-conduct issue before enjoying sovereign immunityâs protections â and this would defeat many of the doctrineâs underlying policies.â Id. We also emphasized that the Legislature had enacted comprehensive schemes that allow contracting parties to resolve breach-of-contract claims against the government. Id. By providing these avenues for redress, the Legislature has balanced competing private and public interests â a balance that would be thwarted if we allowed waiver-by-conduct exceptions in breach-of-contract actions against the government.
IT-Davy is dispositive here. As in that case, we reject the invitation to recognize a waiver-by-conduct exception in a breach-of-contract suit against a governmental entity. The court of appeals correctly held that such an exception did not apply. 277 S.W.3d at 143.
III. Sharylandâs claims against the contractors
A. The economic loss rule
there is not one economic loss rule broadly applicable throughout the field of torts, but rather several more limited rules that govern recovery of economic losses in selected areas of the law. For example, the rules that limit the liability of accountants to third parties for harm caused by negligence or that save careless drivers from liability to the employer of a person injured in an auto accident may be fundamentally distinct from the ones that bar compensation in tort for purely economic losses resulting from defective products or misperfor-mance of obligations arising only under contract.
Vincent R. Johnson, The Boundary-Line Function of the Economic Loss Rule, 66 Wash. & Lee L.Rev. 523, 534-35 (2009); see also Jay M. Feinman, The Economic Loss Rule and Private Ordering, 48 Ariz. L.Rev. 813, 813 (2006) (âThe most general statement of the economic loss rule is that a person who suffers only pecuniary loss through the failure of another person to exercise reasonable care has no tort cause of action against that person. Because the rule applies to a diverse range of situations, there is not one economic loss rule, but several.â).
1. Application of the rule in Texas
The economic loss rule was initially formulated to set perimeters in product liability cases. See Eddward P. Ballinger, Jr. & Samuel A. Thumma, The History, Evolution and Implications of Arizonaâs Economic Loss Rule, 34 Ariz. St. L.J. 491, 492 (2002). As we recently described it, â[t]he economic loss rule applies when losses from an occurrence arise from failure of a product and the damage or loss is limited to the product itself.â Equistar, 240 S.W.3d at 867; see also Seely v. White Motor Co., 63 Cal.2d 9, 45 Cal.Rptr. 17, 403 P.2d 145, 151 (1965).
Our earliest articulation of the economic loss rule came in a product liability case. See Nobility Homes of Tex., Inc. v. Shivers, 557 S.W.2d 77 (Tex.1977). In Nobility Homes, a mobile-home purchaser sued the manufacturer for defective workmanship and materials. Id. at 77-78. We held that the plaintiff could ânot recover his economic loss under section 402A of the Restatement (Second) of Torts,â
We reprised this theme six years later in Mid Continent Aircraft Corp. v. Curry County Spraying Service, Inc., 572 S.W.2d 308, 812-13 (Tex.1978). Curry bought an overhauled aircraft from Mid Continent and sued after the plane crashed. Id. at 309-10. We rejected a strict product liability theory in favor of an implied warranty action under the UCC, because Curryâs economic loss (damage to the plane itself) was âmerely loss of value resulting from a failure of the product to perform according to the contractual bargain and therefore is governed by the Uniform Commercial Code.â Id. at 311. We distinguished cases
Subsequently, in Jim Walter Homes, Inc. v. Reed, 711 S.W.2d 617, 618 (Tex.1986), we examined the difference between contract duties and tort duties arising under contractual relationships. That case involved a claim by homeowners against their builder, and we had to decide whether an independent tort supported an award of exemplary damages against the builder. Jim Walter Homes, 711 S.W.2d at 617. Because the injury resulted from negligent construction, we held that such disappointed expectations could âonly be characterized as a breach of contract, and breach of contract cannot support recovery of exemplary damages.â Id. at 618.
Relying on the tort and contract distinctions articulated in Jim Walter Homes, we again applied the economic loss rule in Southwestern Bell Telephone Co. v. DeLanney, 809 S.W.2d 493 (Tex.1991). In that case, we considered âĂwhether a cause of action for negligence is stated by an allegation that a telephone company negligently failed to perform its contract to publish a Yellow Pages advertisement.â DeLanney, 809 S.W.2d at 493. We held that, because the plaintiff sought damages for breach of a duty created under contract, as opposed to a duty imposed by law, tort damages were unavailable. Id. at 494. Quoting Jim Walter Homes, we explained that
[t]he acts of a party may breach duties in tort or contract alone or simultaneously in both. The nature of the injury most often determines which duty or duties are breached. When the injury is only the economic loss to the subject of a contract itself the action sounds in contract alone.
Id. at 495 (quoting Jim Walter Homes, 711 S.W.2d at 618).
We later declined to extend DeLanney to a fraudulent inducement claim, even when the claimant suffered only economic losses to the subject of a contract. See Formosa Plastics Corp. USA v. Presidio Engârs & Contractors, Inc., 960 S.W.2d 41, 46 (Tex.1998). We reasoned that Texas law has long imposed a duty to refrain from fraudulently inducing a party to enter into a contract, and our prior decisions made it clear that tort damages were not precluded simply because a fraudulent representation caused only an economic loss. Id. at 46-47.
Thus, we have applied the economic loss rule only in cases involving defective products or failure to perform a contract. In both of those situations, we held that the partiesâ economic losses were more appropriately addressed through statutory warranty actions or common law breach of contract suits than tort claims. Although we applied this rule even to parties not in privity (e.g. a remote manufacturer and a consumer),
The court of appeals relied on a different sort of economic loss rule â one that says that you can never recover economic damages for a tort claim â to reject Sha-rylandâs negligence claim against the contractors. That court analyzed whether Sharylandâs claim was one for property damage or for purely economic loss and concluded it was the latter. 277 S.W.3d at 154-55 (noting that âsome physical destruction of tangible property must occurâ for there to be property damage). Because there was no evidence that the sewer lines had contaminated the water supply, the court of appeals reasoned, Sharyland had not suffered property damage, and the economic loss rule precluded a damage award. Id.
There are at least two problems with this analysis. First, it both overstates and oversimplifies the economic loss rule. See, e.g., Giles v. GMAC, 494 F.3d 865, 874 (9th Cir.2007) (noting that âmany courts have stated in overly broad terms that purely economic losses cannot be recovered in tortâ but â[s]uch broad statements are not accurateâ). To say that the economic loss rule âpreclude[s] tort claims between parties who are not in contractual privityâ and that damages are recoverable only if they are accompanied by âactual physical injury or property damage,â 277 S.W.3d at 152-53, overlooks all of the tort claims for which courts have allowed recovery of economic damages even absent physical injury or property damage. See, e.g., Formosa, 960 S.W.2d at 47; see also Powers & Niver, 23 Tex. Tech L.Rev. at 492 (noting that âthe âeconomic lossâ rule has never been a general rule of tort law; it is a rule in negligence and strict product liabilityâ and observing that â[p]ure economic loss is commonly recoverable in certain tortsâ). Among these are negligent misrepresentation,
Moreover, the question is not whether the economic loss rule should apply where there is no privity of contract (we have already held that it can), but whether it should apply at all in a situation like this. Merely because the sewer was the subject of a contract does not mean that a contractual stranger is necessarily barred from suing a contracting party for breach of an independent duty. If that were the case, a party could avoid tort liability to the world simply by entering into a contract with one party. The economic loss rule does not swallow all claims between contractual and commercial strangers.
The court of appealsâ blanket statement also expands the rule, deciding a question we have not â whether purely economic losses may ever be recovered in negligence or strict liability cases. This involves a third formulation of the economic loss rule, one that does not lend itself to easy answers or broad pronouncements. See, e.g., Johnson, 66 Wash. & Lee L.Rev. at 527 (noting that outside the realm of product- or contract-related claims, âthe operation of the economic loss rule is not well mapped, and whether there is a âruleâ at all is a subject of contentionâ).
The contractors argue that permitting recovery in this case will upend the industry because construction contracts are negotiated based on anticipated risks and liabilities, and allowing parties like Shary-land to recover in tort would skew that analysis. Construction defect cases, however, usually involve parties in a contractual chain who have had the opportunity to allocate risk, unlike the situation faced by Sharyland. While it is impossible to analyze all the situations in which an economic loss rule may apply, it does not govern here. The rule cannot apply to parties without even remote contractual privity, merely because one of those parties had a construction contract with a third party, and when the contracting party causes a loss unrelated to its contract.
B. Third party beneficiary status
Sharyland argues that there was evidence to support the jury finding that Sharyland was a third party beneficiary of the agreements between Alton and the contractors. The court of appeals disagreed, holding that Sharyland was âno more than an incidental beneficiaryâ to the contract. 277 S.W.3d at 152. Because the contracts entered into between Alton and the contractors make no reference to Sha-ryland and indicate no intention to confer a benefit on it, we agree with the court of appeals that Sharyland was not a third party beneficiary of those contracts.
As noted by the court of appeals, â[tjhere is a presumption against conferring third-party beneficiary status on non-contracting parties.â Id. at 149; see also S. Tex. Water Auth. v. Lomas, 223 S.W.3d 304, 306 (Tex.2007) (per curiam). We stated as much in another case involving a
[i]n deciding whether a third party may enforce or challenge a contract between others, it is the contracting partiesâ intent that controls.... The intent to confer a direct benefit upon a third party âmust be clearly and fully spelled out or enforcement by the third party must be denied.â ... Incidental benefits that may flow from a contract to a third party do not confer the right to enforce the contract.... A third party may only enforce a contract when the contracting parties themselves intend to secure some benefit for the third party and entered into the contract directly for the third partyâs benefit.
Id. (citations omitted). Importantly, â âthe fact that a person is directly affected by the partiesâ conduct, or that he âmay have a substantial interest in a contractâs enforcement, does not make him a third-party beneficiary.â â Fleetwood Enters. Inc. v. Gaskamp, 280 F.3d 1069, 1075 (5th Cir.2002) (applying Texas law and quoting Loyd v. ECO Res., Inc., 956 S.W.2d 110, 134 (Tex.App.-Houston [14th Dist.] 1997, no pet.)).
Sharyland does not meet the criteria necessary to confer third party beneficiary status. Sharyland is neither mentioned in the contracts themselves, nor is there evidence that Alton and the contractors intended to confer a direct benefit on Shary-land. Alton contracted with Carter & Burgess to manage construction of the sewer system; with Turner, Collie & Bra-den to engineer and inspect the system; and with Cris Equipment Company to build the system. While Sharyland may incidentally benefit from the contractorsâ promises to place the sewer lines in accordance with the plans and specifications; the contract falls far short of âclearly and fully spelling] outâ such an intent. Lomas, 223 S.W.3d at 306. The primary purpose of these agreements was to provide for the construction of a sewer system in Alton, not to benefit Sharyland. Cf. Basic Capital Mgmt., Inc. v. Dynex Commercial, Inc., 348 S.W.3d 894, 900 (Tex.2011) (noting that contract had âno purpose whateverâ other than to benefit third party). We agree with the court of appeals that Shary-land was not a third party beneficiary of the agreement between Alton and the contractors. 277 S.W.3d at 152.
IV. Administrative Code Chapter 30, section 317.13
As an alternate basis for affirming the court of appealsâ judgment, the contractors urge that the trial court incorrectly held that section 317.13 of the Texas Administrative Code, which was in effect at the time the dispute arose, applied to the sewer lines in this case.
Section 317.13 provides, in pertinent part:
The following rules apply to separation distances between potable water and wastewater plants, and waterlines and sanitary sewers.
(1) Waterline/new sewer line separation. When new sanitary sewers are installed, they shall be installed no closer to waterlines than nine feet in all di*422 rections. Sewers that parallel waterlines must be installed in separate trenches. Where the nine-foot separation distance cannot be achieved, the following guidelines will apply.
(A) Where a sanitary sewer parallels a waterline, the sewer shall be constructed of cast iron, ductile iron, or PVC meeting ASTM specifications with a pressure rating for both the pipe and joints of 150 psi. The vertical separation shall be a minimum of four feet between outside diameters. The sewer shall be located below the waterline.
(B) Where a sanitary sewer crosses a waterline and the sewer is constructed of cast iron, ductile iron, or PVC with a minimum pressure rating of 150 psi, an absolute minimum distance of six inches between outside diameters shall be maintained. In addition, the sewer shall be located below the waterline where possible and one length of the sewer pipe must be centered on the waterline.
30