Opinion
BORDEN, J.
The dispositive issues in this certified appeal are: (1) whether the seven year limitation period of General Statutes § 52-584a,1 or the two year limitation *295period of General Statutes § 52-584,2 2 applies to this action; and (2) whether it is the intent of the promisee of a contractual obligation, rather than the intent of both of the parties to the contract, which determines whether a third party is a beneficiary of the contract in question. The plaintiff, Joseph Grigerik, appeals, and the defendants,3 Gary Sharpe and Angus McDonald-*296Gary Sharpe and Associates, Inc., cross appeal from the judgment of the Appellate Court. The Appellate Court concluded that: (1) as to the plaintiffs negligence count against the defendants, the two year statute of limitations of § 52-584 applied; and (2) as to the breach of contract count against the defendants by the plaintiff, as a third party beneficiary of the contract, the trial court improperly instructed the jury that it must find that both the contracting parties intended the plaintiff to be a third party beneficiary of the contract. We conclude that: (1) the seven year limitations period of § 52-584a applies to this action; and (2) it is the intent of both parties to a contract that determines whether a third party is a beneficiary of a contract. Accordingly, we reverse the judgment of the Appellate Court.
The plaintiff brought this action against the defendants in two counts.4 **4 The first count alleged a breach of the contract between the defendants and Edward Lang, the plaintiffs predecessor in title to an unimproved plot of land in Killingworth. Pursuant to the contract, the defendants had agreed to perform professional engineering services, namely, certain soil testing and site planning necessary to the construction of a septic system that would comply with state and local regulations. The plaintiff claimed to be a third party beneficiary of that contract. The second count was based on the negligence of the defendants in performing these professional services.
With respect to the negligence count, the defendants pleaded, as a special defense, the two year limitations *297period of § 52-584. The trial court ruled, however, that the negligence action was not barred by that provision. With respect to the breach of contract count, the trial court instructed the jury that, in order for the plaintiff to recover as a third party beneficiary to the contract, he was required to establish that he was either an intended, a contemplated, or a foreseeable beneficiary of the contract between Lang and the defendants.5 In response to specific interrogatories, the jury found that, although the plaintiff was neither an intended nor a contemplated beneficiary, he was a foreseeable beneficiary of the contract. The jury found for the plaintiff on both counts, and the trial court rendered judgment for the plaintiff on the verdict.
On the defendantsâ appeal to the Appellate Court, the court concluded that the two year statute of limitations provided by § 52-584 applied so as to bar the plaintiffs negligence count. With respect to the breach of contract count, the Appellate Court concluded that the trial courtâs instructions were flawed in two respects: first, in favor of the plaintiff, by permitting him to recover as a foreseeable, rather than an intended beneficiary *298of the contract; second, in favor of the defendants, by requiring that both parties, rather than just the promisee of the contractual obligation in question, intended to benefit the plaintiff. Accordingly, the Appellate Court reversed the judgment of the trial court, ordered that judgment be rendered for the defendants on the negligence count, and ordered a new trial on the breach of contract count.6 ****6 Grigerik v. Sharpe, 45 Conn. App. 775, 798, 699 A.2d 189 (1997). Both the plaintiff and the defendants sought certification to appeal, and this appeal followed.7
On his appeal regarding the negligence count, the plaintiff claims that the Appellate Court improperly concluded that the two year limitation period of § 52-584 applied so as to bar the action. On their cross appeal regarding the breach of contract count, the defendants *299claim that the Appellate Court improperly concluded that the intent of the promisee only, rather than the intent of both contracting parties, determines whether there is a third party beneficiary to a contract. We agree with the contentions of both the plaintiff and the defendants.
The Appellate Court opinion sets forth the following facts that the jury reasonably could have found. âIn 1983, Edward Lang purchased a tract of undeveloped land on Reservoir Road in the town of Killingworth. The property contained a hill, a marshy area, trees and many vines and bushes. Lang removed some of the trees and bushes and also obtained the release of a power line easement that the utility company no longer needed. Because the land was adjacent to a reservoir, it was within a designated watershed area.
âIn 1985, Lang negotiated with the plaintiff for the sale of the land. The plaintiff offered $9000 for the property âas is.â He told Lang, however, that he would pay $16,000 if Lang would do the work necessary to obtain the townâs approval of the land as a building lot. Lang agreed to do so. Both of them accompanied the sanitarian for Killingworth when he examined the property. He told them that, because the land was within a watershed district, they needed an engineer to prepare a site plan for drainage.
âLang hired the defendant Gary Sharpe, a professional engineer, and the corporate defendant [Angus McDonald-Gary Sharpe and Associates, Inc.] to prepare a site plan, to design a subsurface sanitary sewage disposal system and to perform the necessary soil testing. Lang told Sharpe that he needed the site plan in order to obtain approval of the land as a building lot and that he had a buyer for the land if the town granted approval.8 *300Sharpe did some of the work necessary for the application and various employees of his firm performed the remainder. They completed their work on the site plan on October 16, 1985. After receiving the site plan from Sharpe, Lang presented it to the Killingworth inland wetlands commission, which granted its approval. On November 19,1985, Lang sold the property to the plaintiff for $16,000, as they had agreed.
âIn the spring of 1986, the plaintiff cleared the land and applied to the town sanitarian for the permits necessary to begin construction of a house in August. The new town sanitarian for Killingworth denied the plaintiffs application for a building permit even though his predecessor had told the plaintiff that the septic system would be approved. The new sanitarian said he was concerned about the suitability of the soil conditions and whether the percolation tests had been performed in the presence of the previous sanitarian. He told the plaintiff that additional percolation tests would have to be performed by an engineer in the presence of a representative of the state department of health (department) during the following spring when the soil would be saturated.
âWhen the percolation tests were performed on March 5, 1987, it was concluded that a curtain drain would have to be installed on the land in order to control the seasonally high groundwater. After the plaintiff had constructed the curtain drain, more percolation tests were completed and submitted to the department. On May 20, 1987, that department informed the plaintiff that the tests indicated that the land was unsuitable for a septic sewage disposal system. Additional percolation testing was done in the spring of 1989 in the presence of a department representative, who determined that the tests indicated that minimum public health standards for a septic system could not be met and that the building permits could not be issued.
*301âThe plaintiff commenced this action by service on Sharpe on September 20, 1989, and, pursuant to a motion to cite in an additional defendant, his corporation was served on June 5, 1991. After a trial, the jury found the issues for the plaintiff and rendered a verdict for damages of $44,024, including interest, on both the negligence and breach of contract counts of the complaint.â Grigerik v. Sharpe, supra, 45 Conn. App. 777-79.
I
We first consider the plaintiffs claim, asserted in his appeal; see footnote 7 of this opinion; that the Appellate Court improperly concluded that § 52-584 applied to this action against a professional engineer for negligent soil testing and the negligent design of a site plan. The plaintiff claims that the seven year statute of limitations of § 52-584a; see footnote 1 of this opinion; rather than the two year statute of limitations of § 52-584; see footnote 2 of this opinion; governs the negligence portion of this action. The defendants contend that the Appellate Court properly determined that § 52-584 applies and that the negligence count was therefore barred by the statute of limitations. We conclude that § 52-584a provides the statute of limitations applicable to the plaintiffs negligence claim and that, therefore, the claim was timely brought.
âThe process of statutory interpretation involves a reasoned search for the intention of the legislature. ... In other words, we seek to determine, in a reasoned manner, the meaning of the statutoiy language as applied to the facts of this case, including the question of whether the language actually does apply. In seeking to determine that meaning, we look to the words of the statute itself, to the legislative history and circumstances surrounding its enactment, to the legislative policy it was designed to implement, and to *302its relationship to existing legislation and common law principles governing the same general subject matter.â (Citation omitted; internal quotation marks omitted.) United Illuminating Co. v. New Haven, 240 Conn. 422, 431, 692 A.2d 742 (1997).
In 1986, the Appellate Court was presented with the issue of whether § 52-584 or General Statutes (Rev. to 1985) § 52-584a applied to a negligence action against an architect and a professional engineer. R.A. Civitello Co. v. New Haven, 6 Conn. App. 212, 504 A.2d 542 (1986). Focusing on the language of the statute as it existed in 1986, prior to being amended later that same year,9 particularly on the language found in subsection *303(a) of § 52-584a â â[notwithstanding any provision of the general statutes,â and in subsection (d) of § 52-584a â â[n]othing in this section shall be construed to extend the period prescribed by the laws of this state for the bringing of any action,â the Appellate Court held that â[t]he intent of the seven year statute, as its clear mandate, was to create a seven year absolute maximum on actions against architects and engineers, based upon the finite barrier of substantial completion . . . while leaving any other lesser limitations in effect.â (Emphasis added.) Id., 229.10 Specifically, although the Appellate Court recognized that it could âbe argued that the fact that contract and tort actions are specifically mentioned in General Statutes [Rev. to 1985] § 52-584a evidences an intent that the new seven year statute be the statute of limitations for actions involving architects and engineersâ; id., 224; the court determined that this inference was rebutted âby the opening phrase of General Statutes [Rev. to 1985] § 52-584a which states notwithstanding any provision of the General Statutes, by the language of [General Statutes (Rev. to 1985)] § 52-584a (d), and by the entire background of [General Statutes (Rev. to 1985)] § 52-584a.â (Internal quotation marks omitted.) Id. The Appellate Court held, therefore, that § 52-584, rather than General Statutes (Rev. to 1985) § 52-584a, applied to the city of New Havenâs *304third party action against an architect and a structural engineering company.
R.A. Civitello Co. was decided in February, 1986. By April, 1986, however, the legislature already had considered and passed Public Acts 1986, No. 86-266, § 2 (P.A. 86-266).11 Both the language and the legislative history of that enactment indicate the legislatureâs intent to overturn R.A. Civitello Co. and to provide a seven year statute of limitations for certain actions against architects and engineers, rather than a two year statute of limitations coupled with a seven year statute of repose. Public Act 86-266 amended General Statutes (Rev. to 1985) § 52-584a by deleting the introductory phrase, â[notwithstanding any provision of the general statutes,â from subsection (a), and the language of subsection (d), â[n]othing in this section shall be construed to extend the period prescribed by the laws of this state for the bringing of any action.â The legislature, therefore, amended General Statutes (Rev. to 1985) § 52-584a so as to remove the precise language relied upon by the Appellate Court in R.A. Civitello Co. to conclude that that statute was solely a statute of repose. As a result, the language of § 52-584a; see footnote 1 of this opinion; now contains no reference to any other statute, and commences with language that is similar to the language that begins other statutes that we previously have construed as operating, at least in part, as statutes of limitations. See, e.g., General Statutes § 52-577, governing actions based in tort (â[n]o action founded upon atort shall be broughtâ); General Statutes § 52-577a, governing actions based on product liability (â[n]o product liability claim . . . shall be broughtâ); General Statutes § 52-576, governing actions based in contract (â[n]o action for an account . . . shall be broughtâ). Moreover, in discussing the proposed *305amendments to General Statutes (Rev. to 1985) § 52-584a, Representative Martin M. Looney stated: âWe currently have in our statutes, Mr. Speaker, a seven year statute of limitations for actions against architects and engineers involving deficiencies in design and planning contract administration and so on. What this amendment would do is ensure that seven year statute would apply and that a shorter statute such as the three year general negligence standard or the six year statute on contract matters would not be superimposed on the statute regarding architects. This is to correct a problem that was highlighted, Mr. Speaker, in the case of [R.A. Civitello Co. v. New Haven, supra, 6 Conn. App. 212] decided by the Appellate Court earlier this year . . . .â (Emphasis added.) 29 H.R. Proc., Pt. 11, 1986 Sess., pp. 4127-28. Finally, commenting on the changes to General Statutes (Rev. to 1985) § 52-584a resulting from P.A. 86-266, Senator Kenneth T. Hampton stated: âHouse Amendment âAâ adds the provision changing the statute of limitations to seven years in cases where the statute of limitations were fewer than seven years to apply for civil actions against architects and engineers.â 29 S. Proc., Pt. 9, 1986 Sess., p. 3072.
Our conclusion that § 52-584a constitutes a seven year statute of limitations for certain actions against architects and engineers, however, does not end our inquiry. The defendants argue that, as the Appellate Court concluded, § 52-584a does not apply to this action because there was no âimprovementâ to real property, as that phrase is used in the statute, from which the seven year period could begin to run. In the defendantsâ view, in order for there to have been an âimprovementâ so as to trigger the applicability of the statute, there must have been a building erected as a result of the architectâs or engineerâs services. The plaintiff responds that § 52-584a applies to all civil actions against architects and engineers within the scope of their professional services, irrespective of whether they resulted *306or were intended to result in a building or structure, and, in the alternative, that the soil testing and design of the septic system in this case constituted an improvement as contemplated by the statute. Although we disagree with the breadth of the plaintiffs arguments, we also disagree with the narrowness of the defendantsâ arguments. We conclude that the negligence at issue in this case related to an improvement as contemplated by the statute and that, under the circumstances of this case, § 52-584a applies.
Section 52-584a (a) provides in relevant part: âNo action or arbitration, whether in contract, in tort, or otherwise, (1) to recover damages (A) for any deficiency in the design, planning, contract administration, supervision, observation of construction or construction of an improvement to real property . . . shall be brought . . . more than seven years after substantial completion of such improvement.â (Emphasis added.) Moreover, the statute contemplates a completed âimprovementâ to real property in its principal application. Section 52-584a (c) provides in relevant part that âan improvement to real property shall be considered substantially complete when (1) it is first used by the owner or tenant thereof or (2) it is first available for use after having been completed in accordance with the contract or agreement covering the improvement
âIn the construction of the statutes, words and phrases shall be construed according to the commonly approved usage of the language; and technical words and phrases, and such as have acquired a peculiar and appropriate meaning in the law, shall be construed and understood accordingly.â General Statutes § 1-1 (a). The phrase âimprovement to real propertyâ is a phrase that has acquired a particular meaning in the law. Without attempting to define the phrase in all its possible nuances and applications, we have little difficulty in *307concluding that an âimprovement to real property,â as commonly understood in the law, â[generally has reference to buildings, but may also include any permanent structure or other development [of the real property in question].â Blackâs Law Dictionary (6th Ed. 1990). Consistent with that understanding, we have defined an improvement to real property as an alteration or development of the property in order to enhance or promote its use for a particular purpose. Metropolitan District v. Barkhamsted, 199 Conn. 294, 302, 507 A.2d 92 (1986). Thus, an âimprovement to real propertyâ as used in § 52-584a ordinarily requires some physical addition to or alteration of the property in question in order to enhance or promote its use for a particular purpose.12
In the ordinary case, therefore, the seven year statute of limitations begins to run from the date of the substantial completion of the improvement for which the architect or engineer performed the services. In this case, therefore, had the proposed septic system that was the subject of the defendantsâ services been installed, the seven years would have begun to run from the date when the system was first used or available for use. The case before us, however, presents the question of whether § 52-584a applies to a situation in which the defect in the professional services rendered was discovered before the intended improvement was begun, and the reason that the improvement was not and could not be effectuated was precisely because of that defect.
âWhen two constructions are possible, courts will adopt the one which makes the [statute] effective and *308workable, and not one which leads to difficult and possibly bizarre results. . . . We consider the statute as a whole with a view toward reconciling its parts in order to obtain a sensible and rational overall inteipretation.â (Internal quotation marks omitted.) Butler v. Hartford Technical Institute, Inc., 243 Conn. 454, 462, 704 A.2d 222 (1997); see Willow Springs Condominium Assn., Inc. v. Seventh BRT Development Corp., 245 Conn. 1, 26-27, 717 A.2d 77 (1998) (â[i]n order to determine the meaning of a statute, we must consider the statute as a whole when reconciling its separate parts in order to render a reasonable overall interpretationâ). It would be irrational to conclude that, in a case such as this, the two year period of § 52-584 applied so that the injured party would have less time to bring his cause of action than if the improvement had been effectuated and the defect discovered after the substantial completion of the intended improvement. Thus, we conclude that, where the improvement to real property contemplated by the architectâs or engineerâs services is not completed because of the defect complained of, § 52-584a, and not § 52-584, applies to the plaintiffs cause of action.13
We recognize that our conclusion that § 52-584a applies where an improvement is planned but never effectuated could result in a situation in which the limitations period might not begin to run until well beyond seven years after the alleged negligence.14 Because that *309is not the situation before us, however, we leave the determination of precisely when the seven year limitations period would begin to run to a case that presents that question. In the present action, the negligence occurred during October, 1985, and the plaintiff commenced this action in September, 1989, less than seven years after final completion of the allegedly defective design. Thus, under any reading of the statute, the action was timely. We conclude, therefore, that the negligence count was not barred by any applicable statute of limitations.
II
We next consider the claim raised in the defendantsâ cross appeal; see footnote 7 of this opinion; that, regarding the plaintiffs breach of contract count, the Appellate Court improperly concluded that it is the intent of the promisee only, rather than the intent of both contracting parties, that determines whether a third party has enforceable rights under a contract. As noted earlier, the jury found that the plaintiff was a foreseeable third party beneficiary of the contract between the defendants and Lang, and returned a verdict in favor of the plaintiff on the plaintiffs breach of contract count.
The plaintiff argues that the Appellate Court properly concluded that, in Stowe v. Smith, 184 Conn. 194, 441 A.2d 81 (1981), we had âchanged the lawâ regarding the rights of third parties to enforce rights under a contract, and that âa mutual intent of the promisor and promisee is no longer necessary for a beneficiary to have a right to enforce the contract.â Grigerik v. Sharpe, supra, 45 Conn. App. 787. Concluding that the trial court improperly had instructed the jury on the breach of contract issue, the Appellate Court reversed *310the judgment and remanded the case to the trial court for a new trial on the breach of contract count. Id., 789. We disagree with the plaintiff and the Appellate Court that the law governing the contract rights of third party beneficiaries has been changed, by Stowe or any other decision of this court, and we conclude that the intent of both parties to a contract determines whether a third party has contract rights as a third party beneficiary. We also conclude, based on the juryâs responses to certain interrogatories, that the jury conclusively found that the plaintiff was not a third party beneficiary of the contract in question. Accordingly, we reverse the judgment of the Appellate Court and direct that judgment be rendered for the defendants on the breach of contract count.
This claim originated with the defendantsâ challenge in the Appellate Court to: (1) the trial courtâs instructions to the jury regarding the determination of whether a third party beneficiary relationship existed between the plaintiff and the defendants; see footnote 5 of this opinion; and (2) the trial courtâs subsequent failure to grant the defendantsâ motion to set aside the verdict, following the juryâs express determination as evidenced by its responses to certain interrogatories,15 that the contracting parties had not intended to benefit the plaintiff. The Appellate Court agreed with the defendants *311that the jury instructions were flawed and prejudiced the defendants because they permitted the plaintiff to recover as merely a foreseeable beneficiary of the contract. The court also concluded, however, contrary to the defendantsâ position, that the trial courtâs flawed instructions prejudiced the plaintiff because they failed to instruct the jury âthat it was the intent of Lang, the promisee, that should determine whether the plaintiff was a third party beneficiary.â On appeal to this court, the defendants maintain that the Appellate Courtâs judgment ordering a new trial on the breach of contract count was based on an incorrect assessment of the law. We agree.
The traditional rule requiring that courts consider the intentions of both parties in construing a contract is well settled. Lar-Rob Bus Corp. v. Fairfield, 170 Conn. 397, 406-07, 365 A.2d 1086 (1976) (â[a] contract is to be construed according to what may be assumed to have been the understanding and intention of the partiesâ); Amalgamated Assn. v. Connecticut Co., 142 Conn. 186, 192, 112 A.2d 501 (1955) (â[i]n interpreting any contract we must seek the intent of the parties expressed thereinâ); Davis v. Davis, 119 Conn. 194, 201, 175 A. 574 (1934) (â[i]t is an accepted principle that where two parties go through the form of entering into a contract, both understanding that there is no intent thereby to incur legal obligations, no contract is in fact createdâ). This rule allows parties to enter into contractual arrangements with the confidence that they subsequently will not find themselves legally bound to unknown or unanticipated obligations.
The law regarding the creation of contract rights in third parties in Connecticut is equally well settled. In Knapp v. New Haven Road Construction Co., 150 Conn. 321, 325, 189 A.2d 386 (1963), we quoted Colonial Discount Co. v. Avon Motors, Inc., 137 Conn. 196, 201, 75 A.2d 507 (1950), and reaffirmed that â[t]he ultimate test *312to be applied [in determining whether a person has a right of action as a third party beneficiary] is whether the intent of the parties to the contract was that the promisor should assume a direct obligation to the third party [beneficiary] and . . . that intent is to be determined from the terms of the contract read in the light of the circumstances attending its making, including the motives and purposes of the parties.â (Emphasis added; internal quotation marks omitted.) Although we explained that âit is not in all instances necessary that there be express language in the contract creating a direct obligation to the claimed third party beneficiaryâ; Knapp v. New Haven Road Construction Co., supra, 326; we emphasized that the only way a contract could create a direct obligation between a promisor and a third party beneficiary âwould have to be, under our rule, because the parties to the contract so intended.â Id.; see also Congress & Daggett, Inc. v. Seamless Rubber Co., 145 Conn. 318, 324, 142 A.2d 137 (1958); Pavano v. Western National Ins. Co., 139 Conn. 645, 648, 96 A.2d 470 (1953); Colonial Discount Co. v. Avon Motors Inc., supra, 200; Byram Lumber & Supply Co. v. Page, 109 Conn. 256, 260, 146 A. 293 (1929).
The requirement that both contracting parties must intend to confer enforceable rights in a third party rests, in part at least, on the policy of certainty in enforcing contracts. That is, each party to a contract is entitled to know the scope of his or her obligations thereunder. That necessarily includes the range of potential third persons who may enforce the terms of the contract. Rooting the range of potential third parties in the intention of both parties, rather than in the intent of just one of the parties, is a sensible way of minimizing the risk that a contracting party will be held liable to one whom he neither knew, nor legitimately could be held to know, would ultimately be his contract obligee.
*313We recently reaffirmed this dual intent standard in Gateway Co. v. DiNoia, 232 Conn. 223, 654 A.2d 342 (1995). Citing to Knapp and numerous analogous cases, we held that â[t]he proper test to determine whether a lease creates a third party beneficiary relationship is whether the parties to the lease intended to create a direct obligation from one party to the lease to the third party.â (Emphasis in original.) Id., 231. The third party beneficiary issue before this court in Gateway Co. was whether the trial court correctly had focused on the intent of the parties to confer a benefit on a plaintiff when evaluating the plaintiffs claim as a third party beneficiary under the contract. Id. We held that â[t]he intent to confer a benefit is irrelevant to the determination of whether [the plaintiff] was a third party beneficiaryâ; id.; rather, the appropriate inquiry is whether âtheparties . . . intended to create a direct obligation from one party ... to the third party.â (Emphasis added.) Id. Although it was not necessary, in Gateway Co., for us specifically to consider whether the intent of one or both contracting parties is relevant to the determination of third party beneficiary rights, our discussion was based expressly on the premise that it is the intent of both parties to a contract that determines these rights. Id.
In Stowe v. Smith, supra, 184 Conn. 194, decided fourteen years prior to Gateway Co., this court had considered a cause of action brought by a plaintiff against the attorney who had made a mistake in drafting the plaintiffs deceased motherâs will. As a result of this mistake, the will in existence at the time of the motherâs death incorrectly provided âthat when the plaintiff attained the age of fifty or upon his earlier death the principal of the trust would be distributed to his issue.â Id., 195. The plaintiffs deceased mother actually had instructed that the will provide âthat one-half of her estate be held in trust for the plaintiff; that when the *314plaintiff attained the age of fifty the assets of the trust would be distributed to him; but that upon the plaintiffs death prior to attaining the age of fifty, the assets of the trust would be distributed to the plaintiffs issue.â Id. According to the complaint, â[t]he defendant [had] informed the mother that he had prepared the will in accordance with her instructions including, specifically, the exact provision she had requested for the plaintiff.â Id.
To the extent that a third party to whom a promisor had made no express commitment was held to have stated a cause of action, Stowe plausibly could be interpreted as having altered Connecticut law regarding the intent necessary for a third party beneficiary to have enforceable rights under a contract. We conclude, however, that the holding in Stowe was consistent with our prior decisions regarding the intent necessary for a third party to possess rights under a contract and, therefore, that the plaintiffs and the Appellate Courtâs reliance on Stowe is misplaced.
Specifically at issue in Stowe was the sufficiency of the plaintiffs complaint. The complaint had alleged that âthe testatrix and the defendant intended that the defendant, by his agreement to prepare [the testatrixâs] will in accordance with her instructions, would assume a direct obligation to the intended beneficiaries of the testatrix.â Id., 196. Thus, the underlying premise of the complaint was that both contracting parties intended that the plaintiff would have enforceable rights under the contract. The question before the court was not whether a dual or singular intent was controlling. The question was, instead, the validity of the attorneyâs argument âthat as a matter of law a promisor cannot intend to assume a direct obligation to a third party unless the promisorâs performance is to be rendered directly to that party.â Id., 197. We rejected that argument, and held that â [contracts for the benefit of a third party *315are enforceable without any requirement that the promisorâs performance be rendered directly to the intended beneficiaryâ; id.; and that the plaintiff had enforceable rights under the contract. Id., 198.
Indeed, in Stowe we began our analysis of the issue by reaffirming the traditional rule governing the creation of third party beneficiary rights under Connecticut law. âWe have stated that a third party seeking to enforce a contract must allege and prove that the contracting parties intended that the promisor should assume a direct obligation to the third party.â (Emphasis added.) Id., 196. It is true that, in a footnote to this sentence, we referred to the differing views of Professors Corbin and Williston.16 Contrary to the plaintiffs assertion, however, we do not read that footnote as adopting these views. In fact, the footnote is, at least in part, addressed to the intent necessary for a third party to claim rights as a donee beneficiary,17 the situation presented in Stowe.
*316Moreover, we disagree with Professor Corbinâs view that the concept of âintentâ is too âobscure and elusiveâ to be helpful in determining the contract rights of third parties. 4 A. Corbin, Contracts (1951) § 776, pp. 14-15. We traditionally have relied on the intent of the parties to determine whether a contract has been formed, as well as to determine the meaning of the terms of the contract. See Davis v. Davis, supra, 119 Conn. 194 (determining whether contract of marriage intended); see also Amalgamated Assn. v. Connecticut Co., supra, 142 Conn. 186 (interpreting contractual phrase according to intent of parties); Finlay v. Swirsky, 103 Conn. 624, 635, 131 A. 420 (1925) (same). We are unpersuaded, therefore, that the concept of intent is any more elusive in the context of determining whether third parties have enforceable rights under the contract.
In support of the view that the presence of a third party beneficiary issue is determined solely by the intention of the promisee, the Appellate Court also relied on 2 Restatement (Second), Contracts § 302 (1981), and concluded that â[t]he notion that the promisor and *317promisee must share the same intent is at variance with most authorities.â Grigerik v. Sharpe, supra, 45 Conn. App. 784. Our reading of § 302 of the Restatement (Second) does not support that reliance. That provision provides in relevant part: âUnless otherwise agreed between promisor and promisee, a beneficiary of a promise is an intended beneficiary if recognition of a right to performance in the beneficiary is appropriate to effectuate the intention of the parties and . . . the circumstances indicate that the promisee intends to give the beneficiary the benefit of the promised performance.â 2 Restatement (Second), supra, § 302 (1) (b). Thus, the language of the Restatement (Second) suggests that the right to performance in a third party beneficiary is determined both by the intention of the contracting parties and by the intention of one of the parties to benefit the third party.
We decline, therefore, to alter our traditional test for determining whether a third party has enforceable contract rights. We reaffirm that the intent of both parties, rather than just one of the parties to a contract, determines whether a third party is to be afforded third party beneficiary status under a contract.
Applying this standard to the facts of the present case, we conclude that the plaintiff cannot prevail on his breach of contract claim. The jurors specifically found that the plaintiff had not proven that he was an intended beneficiary of the contract between Lang and the defendants. See footnote 15 of this opinion. The plaintiff, therefore, did not establish that it was the intent of the parties that he be a third party beneficiary of the contract.
Although the jury found that the plaintiff was a foreseeable benefi